Q. Module Assembly Site Preparation?

To set a module on the piles installed on project site, the following preparations shall be made:

The Designer shall provide design elevations and positions (x, y, z coordinates) for all piping tie-in points on the design drawings. It is essential that all site piping inter-module tie-ins can be worked without field modifications.

The Surveyor shall "As-Build" all piping tie-in locations at the module fabrication site. Tie-in x, y, z coordinates shall be "As-Build" referenced to the module supports.

The four corner support columns of the particular module shall be scribed and punch marked with the exact column centreline in each direction. Punch marking and scribing shall be on the:

• Vertical face of the column

• Top of the base plate

• Vertical edge of the base plate

Each support column shall be surveyed to determine its location from the key corner column (A-1) and piping tie-in locations.

The base plate of each support column shall be surveyed to determine the bottom elevation of each corner of the base plate relative to the floor and piping tie-in locations.

Prepare "As-build" drawings of the piping tie-ins and module support elevations and x, y, z coordinates.

Survey data shall be forwarded to the Owner's Site construction support and Home Office, prior to module setting on piles.


Related Discussions:- Module assembly site preparation

Belt tension for v-belt, Belt tension for V-belt: What is V-belt. Dri...

Belt tension for V-belt: What is V-belt. Drive expression of Ratio in belt tension for V-belt Sol: The power from one shaft to the other shaft can be transmitted with t

Compute monitoring and control, Compute Monitoring and Control: These are t...

Compute Monitoring and Control: These are the direct application in which the computer is connected directly to the manufacturing process for the purpose of monitoring or contr

Newer approaches to on-line scheduling, Newer Approaches To On-Line Schedul...

Newer Approaches To On-Line Scheduling  The on-line scheduling has established to be superior option than off-line scheduling upon the shop floor. The on-line scheduling looks

Spot welding of different metals-aluminium and its alloys, Spot welding of ...

Spot welding of different metals-Aluminium and its alloys High currents and shorter welding times are necessary for these materials. Special cleaning of the surface is warrante

Total resistance of the system between the electrodes, The total resistance...

The total resistance of the system between the electrodes consists of (i) The resistance of the work piece R 1 (ii) The contact resistance between the electrodes and the wo

Second gear position- shifting of gear, Second Gear Position: When ge...

Second Gear Position: When gear M2 on the main shaft is in mesh with gear C2 on the countershaft then this is known as second gear position. To rotate free gear M2 with the m

Equations by gauss-jordan method, a) Answer the following equations by Gaus...

a) Answer the following equations by Gauss-Jordan method x 1 +2x 2 +x 3 =8 ; 2x 1 +3x 2 +4x 3 =20; 4x 1 +3x 2 +2x 3 = 16 b) Answer the following equations by Relaxation m

Idle circuit of motorcycle, Idle Circuit : During Idling while the th...

Idle Circuit : During Idling while the throttle valve is almost closed the vacuum is very high at Venturi area and no air-fuel mixture is drawn through the main circuit, as t

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd