Explain the Dynamic or Vibration Tests

Tests of this type, also known as sonic integrity test, involve sub- jecting the element to a single impulsive blow or cyclic load, and measur- ing the response of the element. This response is measured in terms of decaying response. All other things being equal, the response of the ele- ment will depend on the stillness of the element and the naturally inherent damping, both of which are changed by the presence of flaws. Therefore, if there was a change in response between two tests, a close investigation should be carried out to establish a cause.

The system generally employs accelerometers to detect the vi- bration signal. The accelerometers are mounted on the structure to a depth of 30 m below the surface, and the frequency analysis required to compare the vibration signature at various times is carried out by com- puter.


Related Discussions:- Explain the dynamic or vibration tests

Number of segments for segmental linings in tunnelling, Q. Number of segmen...

Q. Number of segments for segmental linings in tunnelling? For the construction of tunnels by segmental linings, choice of the number of segments affects the durability and cos

Timber, defects in timber?

defects in timber?

What are advantages and disadvantage of varnishing, Q. What are advantages ...

Q. What are advantages and disadvantage of varnishing? Varnish is a clear pale solution of a resinous substance ( like amber, common resin, copal, lac, or shellac 0 dissolved i

Advantages and disadvantages of water transport, Advantages and Disadvantag...

Advantages and Disadvantages of Water Transport: The following are the advantages of water transport: (a)        Since the vessels travel on water, no investment is needed

Function of reinforced concrete infill, Function of reinforced concrete inf...

Function of reinforced concrete infill in marine piling system of steel tubular pile with reinforced concrete infill Reinforced concrete is designed to fill void space inside

Calculate surface loading rate for each clarifier, A wastewater plant is op...

A wastewater plant is operating at 10MGD with a suspended solids concentration of 200mg/L. It has 6 clarifiers operating in parallel. Each clarifier is 40 foot in diameter and 10 f

Standard mixes of concrete, In some nations such as Britain, specification ...

In some nations such as Britain, specification for concrete doesn'tusually require cube tests for standard mixes of concrete. Quality control of standard mixes in Britain is achiev

Potential advantages of segmental tunnelling, Q. Potential advantages of se...

Q. Potential advantages of segmental tunnelling when compared with hand-shield pipe-jacking? In segmental tunnelling, jacks are installed at the shield so that itisn't necessar

Inspection and testing, Q. Inspection and testing ? The inspection and ...

Q. Inspection and testing ? The inspection and tests on elastomer and the finished bearings are very important aspects of ensuring a satisfactory performance of the bearing. IR

Plant location and facility layout, Plant Location and Facility Layout: ...

Plant Location and Facility Layout: This unit explain the general definition of Plant location and facility layout. Several factors affecting the location decision of a firm o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd