Explain the Dynamic or Vibration Tests
Tests of this type, also known as sonic integrity test, involve sub- jecting the element to a single impulsive blow or cyclic load, and measur- ing the response of the element. This response is measured in terms of decaying response. All other things being equal, the response of the ele- ment will depend on the stillness of the element and the naturally inherent damping, both of which are changed by the presence of flaws. Therefore, if there was a change in response between two tests, a close investigation should be carried out to establish a cause.
The system generally employs accelerometers to detect the vi- bration signal. The accelerometers are mounted on the structure to a depth of 30 m below the surface, and the frequency analysis required to compare the vibration signature at various times is carried out by com- puter.
Explain the term - Loss of Prestress At the transfer stage, tendons produce compressive stresses in concrete. Sooner or later, the magnitude of these stresses experiences a re
what is reciprocal ranging?
fabrication methods of ironmongery
Seasoning of Timber It is a process by which moisture content in a freshly cut tree is reduced to a appropriate level. The durability of timber is increased by doing so. The se
Principal Stresses and Strains: Principal Stresses and Strains is a very important link in the analysis of solids so as to make sure safe design of different components of str
tape correction
Feactures and uses of distomat
The completion of this assignment will entail the design of the structural fire protection for a simple warehouse building. You will provide a separate engineering calculation and
The inner diameters of a sampling tube and that of a cutting edge are 70 mm and 68 mm correspondingly, their outer diameters are 72 and 74 mm respectively. Verify the inside cle
Construction of Embankment: The following steps describe embankment construction : (a) The ground is cleared and grubbed and all vegetation, grass, roots, etc. are removed
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd