Explain the current maximum output of the process, Operation Management

Assignment Help:

I-mart is a discount optical shop that can fill most prescription orders in around 1 hour. The management is analyzing the processes at the store. There currently is one person assigned to each task below. The optometrist assigned to task B takes an hour off for lunch and the other employees work the entire day.

Task Time

A) Greet/register the patient 2 minutes/patient

B) Optometrist conducts eye exam 25 minutes/patient

C) Frame/lenses selection 20 minutes/patient

D) Glasses made (process can run 6 pairs of glasses at the same time) 60 minutes/patient

E) Final fi tting 5 minutes/patient

For a typical 10-hour retail day (10 a.m.-8 p.m.), the manager would like to calculate the following:

a) What is the current maximum output of the process per day (assuming every patient requires glasses)?

b) If another person were added, where would be the logical place?

c) What effect would a mail order lab (where the glasses are made off-site and returned in 5-7 days) have on the process?


Related Discussions:- Explain the current maximum output of the process

Learning teaching and assessment strateg, Learning Teaching and Assessment ...

Learning Teaching and Assessment Strategy: Key lectures will be delivered and immediately followed up by group tutorials in which the opportunity to critically reflect, analys

How might the imposition of a quota on cell phones impact, Nokia Corporatio...

Nokia Corporation, headquartered in Finland, is a world leader in the cell phone industry. Because much of Finland is heavily forested and sparsely populated, it is difficult and e

What are the advantages of the level capacity strategy, What are the advant...

What are the advantages of the Level capacity strategy? The advantages of the Level capacity strategy: a. Employment of operational resources at all times. b. Efficient p

Explain production system, If all you knew about a production system was th...

If all you knew about a production system was that total daily output was 400 units and the total labour necessary to produce the 400 units was 350 hours, what kind of productivity

Line balancing, What happens if balance doesn''t exist

What happens if balance doesn''t exist

What are the arguments for as against social responsibility, What are the a...

What are the arguments for and against social responsibility on the part of businesses? Please in addition, which set of arguments is more compelling?

Explain the case of ellen moore living and working in korea, The case of El...

The case of Ellen Moore (A) Living and Working in Korea. Look at this case from the point of view of Andrew Kilpatrick. At this point in time, what would you do if you were Andrew?

Approaches for handling customer complaints and listening to, explain appro...

explain approaches for handling customer complaints and listening to customers

Explain the system utilization rate and the probability, Sid Das Brick Dist...

Sid Das Brick Distributors currently employs 1 worker whose job is to load bricks on outgoing company trucks. An average of 24 trucks per day, or 3 per hour, arrive at the loading

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd