Example of manufacturing lead time (mlt), Mechanical Engineering

Example of Manufacturing Lead Time (MLT)

A certain part is generated in a batch size of 100 units. The batch should be routed through five operations to complete the processing of the parts. Average setup time is 3 hr/operation, & average operation time is equal to 6 min (0.1 hr). Average nonoperational time because of handling, delays, inspections, etc., is 7 hours for each operation. Calculate how many days it will take to complete the batch, supposing the plant runs one 8-hr shift/day.


The manufacturing lead time is determined

MLT = 5 (3 + 100 × 0.1 + 7) = 100 hours

At 8 hr/day, this amounts to 100/8 = 12.5 days.

Posted Date: 12/26/2012 8:08:15 AM | Location : United States

Related Discussions:- Example of manufacturing lead time (mlt), Assignment Help, Ask Question on Example of manufacturing lead time (mlt), Get Answer, Expert's Help, Example of manufacturing lead time (mlt) Discussions

Write discussion on Example of manufacturing lead time (mlt)
Your posts are moderated
Related Questions
Illustrated about the term bending moment? Bending Moment The critical section for bending moment for masonry or concrete block walls is half-way between the centre line and

give equivalence of screw jack and friction on an inclined plane

Find out the centroid of the shaded area: Find out the centroid of the shaded area illustrated in Figure (a). Solution The shaded area A may be considered as the

need help with reports on thin thick and combined cylinder theory

Calculated the magnitude of the instantaneous stress: While a concentrated force of 1 kN is applied at the midspan point of a simply supported beam a static deflection of 5 mm

Example of change of enthalpy: Q 0.5kg/s of a fluid flows in steady state process. The properties of fluid at the entrance are measured as p 1 = 1.4bar, density = 2.5k

A new process plant for ore processing is currently being planned. The design is only in the first stage. However, three requirements have already been clearly stated: - The bins s

Steel Rule: A steel rule is used to measure length. It has two scales - in millimeters and inches. These rules are available in market in discrete lengths such as 15, 30, 60 cms.

Find the diameter of drawn tubing (e = 0.0015 mm) to transport 0.002 m 3 /s of 20 o C water over 400 m length so that the head loss does not exceed 30m by using (

Constructive Solid-Geometry Methods (CSG) Constructive models represent a solid as a combination of primitive solids. This modeling technique combine the volumes occupied by ov