Q. Drive an expression for peak manning of a project using Nordes - Rayleigh equation .
Ans Norden Rayleigh curve utilized to approximate software project .
M(t) =Man power utilization
= dy/dt = 2kate-at2 -------------(1)
K = Area under the curve t=time
Integrating eg . (1) with respect to t
Y(t) = k[1-e-at2] ----------------(2)
Differentiating eq (1) with respect to t
M'(t) = d2y/dt2 = 2kae-at2(1-2at2) ---------(3)
Put a=1/2td2 and t=td in eq (1)
M(t) = 2kate-at2 = 2k*1/2t2d *td e-1/2td2*td
= k/tde-1/2 = k/tde1/2
M0 = k/tde1/2
M0 = peak manning of a project .
What is the purpose of timeline chart? The purpose of the timeline chart is to emphasize the scope of the individual task. As set of tasks are given as input to the timeline ch
What are the benefits of evolutionary prototyping? i. Fast delivery of the working system. ii. User is included while developing the system. iii. More useful system can b
Incremental integration testing is permanent testing of an application as new functionality is recommended. This may need that various aspects of an application's functionality are
What is Software? Software is nothing but a collection of computer programs that are related documents that are indented to give desired features, functionalities and improved
List the process maturity levels in SEIs CMM. Level 1: Initial - Few processes are explained and individual efforts are taken. Level 2:Repeatable - To track cost schedule an
What are the assumptions of the execution-time component model? The execution-time component is based on the several assumptions: (1) Tests show the environment in which the
What is meant by Information flow Continuity? When we refine a fundamental model for a system, the information flow continuity should be maintained .ie, input & output to each
What are different severity ratings in a project? There can be 4 types of severity ratings in a table: i.) Severity 1 - Showstoppers - Don't allow application to move at
ZeroJet, a new low cost airline, wants a brand new web-based system to allow people to book seats for flights on-line. They want an automated check in system which has no staff.
Re-Engineering cost factors:- 1) The amount of the software to be re-engineered. 2) The tool support available for re-engineering. 3) The extent of the data conversion
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd