Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Designing water storage tank, Question While designing water storage t...

Question While designing water storage tank , has movement joints be installed? Answer While designing water storage tanks , group joints can be set up in similar w

Bending moment , The internal forces in any cross-section of a symmetric me...

The internal forces in any cross-section of a symmetric member in pure bending are equivalent toa couple M The moment of the couple is referred to as the bending moment in the s

Define unit hydrograph - hydrology, Define Unit Hydrograph UNIT HYDROGR...

Define Unit Hydrograph UNIT HYDROGRAPH: The hydrograph developed for a drainage basin (watershed) from the runoff of a 1 in or 1 cm storm. It is the base hydrograph from which

Write short note on skv process of thermit welding, Q. Write short note on...

Q. Write short note on SKV  process of thermit welding? This term is used for welding by Alumino thermic process with short preheat time. The time required for preheat with pet

Reinforcement in thrust blocks, Reinforcement in thrust blocks In gene...

Reinforcement in thrust blocks In general situation, reinforcement isn't essential for thrust blocks in pressurized pipelines. Though certain amount of reinforcement hasto be

Continuous prestressed concrete beam design , Assignment:-Continuous Prestr...

Assignment:-Continuous Prestressed Concrete Beam Design A cast in-place 3-span prestressed concrete T-beam is to be designed. The T-beam concsists of an 8-in thick reinforced

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd