Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Define bank volume to be stockpiled and used for backfill, An earthwork con...

An earthwork contract was awarded to excavate and backfill the foundation of a proposed 50-ft by 50-ft office building.  The existing grade elevation is 437.5-ft while the sub-base

Determine length of guide bunds, Q. Determine Length of guide bunds? Leng...

Q. Determine Length of guide bunds? Length of a guide bund has to be such that the flow approaching even from behind the guide bund would pass through the bridge with minimum obl

Centroid, use of centroid in civil engineering

use of centroid in civil engineering

Scheming thermal reinforcement, Question What is importance of critical...

Question What is importance of critical steel ratio in scheming thermal reinforcement ? Answer Execution of critical steel ratio resources that in construction joints,

What is rapid sand filter, Q. What is Rapid Sand Filter? A Rapid Sand F...

Q. What is Rapid Sand Filter? A Rapid Sand Filter is a water treatment plant that includes provision for pre treating the water by coagulation and sedimentation for settlement

Elimination of formwork with reasons, Question For a l ong slender structur...

Question For a l ong slender structure similar to beams, propping is compulsory after elimination of formwork with reasons? Answer After concreting, time at which arresting of

Manage civil work design, Ask question #Minimum 1Make a detailed list of al...

Ask question #Minimum 1Make a detailed list of all constraints and requirements to the bridge design00 words accepted#

Explain ductile iron pipes and mild steel pipes, Ductile iron pipes vs. mil...

Ductile iron pipes vs. mild steel pipes as pressurized pipelines For water main pipe size less than 600mm, ductile iron is generally used since internal welding for steel pipe

Structural drawing, Overview   A structure is required to support a conv...

Overview   A structure is required to support a conveyor and various ancillary equipment, between two buildings in an industrial area. It is 12m long and made up of structural s

Dam, how can i prepare a project on dam

how can i prepare a project on dam

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd