Define project schedule financial analysis, Civil Engineering

Assignment Help:

The 6 monthly payment application for the construction of a $70,000,000 University dormitory is analyzed and the summary accounting show: the budgeted cost of work performed is $14,500,000, while the actual cost of work performed is $14,750,000. Calculate the cost status of the project.

Solution: Financial project status is analyzed using the following equations:

BCWS = Budgeted Cost of Work Scheduled = planned costs

ACWP = Actual Cost of Work Performed = actual spent

BCWP = Budgeted Cost of Work Performed = Earned Value

Schedule Variance = BCWP - BCWS

Cost Variance = BCWP - ACWP

Cost Variance = BCWP - ACWP

Cost Variance = $14,500,000 - $14,750,000 =   - $250,000 (over budget)

(1 - ($14,500,000 ÷ $14,750,000)) x 100 = 1.69% over budget

 


Related Discussions:- Define project schedule financial analysis

Calcculate the material costs, A capital improvement project requires the i...

A capital improvement project requires the installation of a property line fence along the 250-ft Northern boundary line.The decorative aluminum fence is constructed of posts space

Resting on several raking piles, Question Should dolphins be designed i...

Question Should dolphins be designed in a rigid manner such as resting on several raking piles? Answer While designing dolphins, they are normally supported on a syste

Explain the term - uniaxial - biaxial -triaxial prestressing, Explain the t...

Explain the term - Uniaxial - Biaxial -Triaxial Prestressing These terms refer to cases when the concrete is prestressed in only one direction, in two mutually perpendicular di

Engineering indicators in case of multi speed restriction, Multi Speed Rest...

Multi Speed Restriction (i.e. existence of two or more than two speed restrictions in continuation) When work of deep screening or sleeper renewal is in progress, there is situ

Determine the co-ordinates of grain-size distribution curve, In a hydromete...

In a hydrometer analysis, 0.5 N of soil was mixed in water to form one litre of uniform suspen- sion. The corrected hydrometer reading after a lapse of 60 min. from the start of se

Describe about the baur-leonhardt system, Describe about the Baur-Leonhardt...

Describe about the Baur-Leonhardt system The Baur-Leonhardt system is included in the third type of anchorages which work under the principle of looping tendon wires at the en

Designing level of landings in piers, Question What is designing leve...

Question What is designing level of landings in piers? Answer Landings are designed as resting place for passengers throughout berthing and deserting of vessels. I

Enumerate the term - superposing the stress variations, Enumerate the term ...

Enumerate the term - superposing the stress variations If the case of concentric pre-stressing is considered, we can appreciate that stress at any section of the beam is compr

Determine the specific gravity of solids, The Atterberg limits of a clay so...

The Atterberg limits of a clay soil are: Liquid limit = 63%, Plastic limit = 40%, and shrinkage limit = 27%. If a sample of this soil has a volume of 10 cm 3 at the liquid limit a

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd