Data Warehousing Job Scheduling, Database Management System

1) Define a job scheduling strategy that will meet business requirement of reporting availability by 6am CST for the following cubes? Show the job scheduling dependencies in a pictorial form so that it is easy to understand.
a. Finance cube (3 hours to build)
b. Warranty cube (4 hours to build)
c. Order cube (2 hours to build)
d. Customer master data (30 min run time)
e. Vendor master data (60 min run time)
f. Product master data (60 min run time)
g. Other Master data (2 hour run time)
Finance and Order cubes cannot run together.
Posted Date: 4/2/2013 12:16:04 AM | Location :







Related Discussions:- Data Warehousing Job Scheduling, Assignment Help, Ask Question on Data Warehousing Job Scheduling, Get Answer, Expert's Help, Data Warehousing Job Scheduling Discussions

Write discussion on Data Warehousing Job Scheduling
Your posts are moderated
Related Questions
The State of Newyork certifies firefighters throughout state keep track all of them, as well as the state’s of fire departments. Each fire department has unique department number

When are two schedules said to be view equivalent?     Ans: Two schedules that is denoted as S and S' are said to be view equivalent if the subsequent three conditions are met

please i request for your assistance in developing a case-based online phone repair

I want a script that will run, and update my virtual machine's LAN settings (proxy server and port), and also re-configure the Firefox User Agent. I want a script that will run,

What is system catalog or catalog relation? How is better known as? A RDBMS maintains a explanation of all the data that it contains, information about every relation and index

What are stand-alone procedures? Procedures that are not part of a package are called as stand-alone because they independently defined. A good example of a stand-alone procedu

i need help for assignment ..

Explain the function of input controls. Identify four types of input control and explain the function of each. Provide an example of a data integrity error that could occur i

Explain the rules for creating a labelled precedence graph for testing view serializability.            Ans: A schedule S is view serializable if it is view equivalent to a ser

What are the two main goals of parallelism? Load -balance multiple small accesses, so that the  throughput of such accesses enhances. Parallelize large accesses so that the res