Already have an account? Get multiple benefits of using own account!
Login in your account..!
Remember me
Don't have an account? Create your account in less than a minutes,
Forgot password? how can I recover my password now!
Enter right registered email to receive password!
QuestionIf on-site slump test fails, is it necessary that engineers allow a contractor to continue concreting works? AnswerThis is an extremely traditional question raised by many graduate engineers. In fact, there are two schools of idea regarding this issue. The first school of thought is rather straightforward- contractor fails to fulfil with contractual requests and therefore as per G. C. C. Clause 54 (2) (c) engineer might order suspension of entitled to any claims of charge which is core concern for mainly engineers. This is contractual power given to Engineer in case of any failure in tests essential by contract; although some engineers argue that slump tests are not as major as other tests similar to compression test. The second school of thought is to let the contractor to continue their concreting works and later on request the contractor to prove that the finished works comply with other requirements as in compression test. This is based upon a belief that workability is mostly necessary to achieve design concrete compression strength. In case compression test also fails, contractor has to demolish and reconstruct works accordingly. In fact, this is a passive method of treating construction works and is not recommended since of following cause-
(i) Workability of freshly placed concrete is related not only to strength but also to stability of material. Still if in future compression test passes, failing in slump test point out that it might have adverse impact to stability of completed concrete structures. (ii) In case compression test fails, contractor has to position extra time and resources to remove work and reconstruct them on one occasion again and this slows down progress of works significantly. Hence, present of such likely probability of occurrence, why shouldn't Engineer exercise his power to stop contractor and save these extra time and cost?
Maintenance of Drainage: Maintenance of drainage will ensure that the run-off is taken away from the runway efficiently. The side ditches and buried pipes should be cleaned r
Aplease provide tables for each design mix and also the, high early strengh.l thanks
causes for decay of timber
wmm how can test depth wise
Question General requirement for Civil Engineering Works in 1992 Edition, Clause 15.09 details that tying wires for strengthening adjacent to and above Class F4 and F5 closes must
#question a pilot entering a bay on course 60.3 degrees at speed 12 miles per hour sees a light bearing 37.3 true and 20 minutes later he sees it bearing 20.0 degrees true. if he k
How do we overcome obstacle like river in chain survey?
Gabions are wire mesh boxes that are filled with stones and they areplaced in an orderly pattern to act as a single gravity retaining wall. Meshes or Lacing wires are designed t
Question In case of concrete pavement, why is requirement of 95% by mass of quartz grains are specified in contract? Answer In universal Specification of Civil Enginee
Step by step rehabilitation strategies with drawing, figures, and illustrations
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd