Compute the standard time for each work, Operation Management

Assignment Help:

The Arkade Company has decided to use a 15 percent allowance factor based on job time. Calculate the standard time for each work element and for the total job. The frequency equals 1 for all work elements. (Round your answers to 3 decimal places, the tolerance is +/-0.002.)
Work Element Mean Observed Time (minutes) Perfomance Rating Factor ST
1 1.20 0.95
2 1.00 0.85
3 0.80 1.10
4 0.90


Related Discussions:- Compute the standard time for each work

What is average costumer waits time in line, A newly opened car wash statio...

A newly opened car wash station has a car wash machine. The machine washes each car in a constant rate of 5 minutes per car. It has been estimated that costumers will arrive accord

Explain the attitudes or traits of an engineer, Describe the attitudes or t...

Describe the attitudes or traits of an engineer that make the engineer unqualified to be a manager

Explain how to create a living, What would you suggest to companies on how ...

What would you suggest to companies on how to create a living, adapting marketing plan?

Greater flexibility of core staff in an organisation, How is greater flexib...

How is greater flexibility of core staff achieved in an organisation? Greater flexibility of core staff into an organisation is accomplished by the follow: a. Shorter term a

Identify business strategy and manufacturing strategy. , Your company has ...

Your company has been invited to look at possible improvements to the manufacturing system at Fly Fishing Reels.  Your colleague has already visited the company to collect the atta

Why knowledge is vital supervisor''s tactical planning, Why should a first-...

Why should a first-line supervisor understand the organization's objectives? Why is this knowledge important to the supervisor's tactical planning?

Scope of job design - process design, Scope of Job Design - Process Design ...

Scope of Job Design - Process Design When designing any job, three requirements must be met simultaneously: technical feasibility, economic feasibility and behavioural feasibi

Explain nominal work groups and the delphi techniques, Nominal work groups ...

Nominal work groups and the Delphi Techniques are used as part of which risk management process? Answer Risk identification Risk assessment Risk monitoring and control

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd