Compare the productivity and difficulty, Software Engineering

Assignment Help:

Q. Compare the Productivity and difficulty?

Productivity refers to metrics as well as measures of output from production processes per unit of input. Productivity P perhaps conceived of as a metrics of the technical or engineering efficiency of production. In software project planning the productivity is defined as the number of lines of code developed per person-month

Difficulty The ratio (K/td 2) where K is software development cost as well as td is peak development time is called difficulty and denoted by D which is measured in person/year.

D= (K/td 2)

The relationship demonstrates that a project is more difficult to develop when the manpower demand is high or when the time schedule is short.

Putnam has experiential that productivity is proportional to the difficulty Pa Db


Related Discussions:- Compare the productivity and difficulty

What is a real time system, What is a Real time system? Real time syste...

What is a Real time system? Real time system is a software system in which the correct functionalities of the system are dependent upon results formed by the system and the tim

Explain productivity, Productivity Productivity refers to metrics and c...

Productivity Productivity refers to metrics and calculates of output from production processes, per unit of input. Productivity P may be conceived of as a metrics of the techni

How the case tools are classified, How the CASE tools are classified? C...

How the CASE tools are classified? CASE tools can be classified by A. By function or use B. By user type(e.g. manager,tester),or C. By stage in software engineering pr

What is the use of knowledge of risk acceptance to engineers, What is the u...

What is the use of knowledge of risk acceptance to engineers?  The past experience and historical data give better information about safety of products designing there are stil

Explain project estimation techniques, Question: a) List and explain t...

Question: a) List and explain three project Estimation techniques. b) During an estimation exercise, a work breakdown structure (WBS) is used as checklist for the activitie

What is the key process areas, What is the Key Process Areas SEI has a...

What is the Key Process Areas SEI has associated key process areas(KPAs) with every maturity level. KPA is an indicative measurement of goodness of software engineering functi

What are the elements of analysis model, What are the elements of Analysis ...

What are the elements of Analysis model? i. Data Dictionary ii. Data Flow Diagram iii. Entity Relationship Diagram iv. State Transition Diagram v. Process specifica

Script file, how to make script file volume of pyramid

how to make script file volume of pyramid

Illustrate the symbols of a data flow diagram, Symbols of a data flow diagr...

Symbols of a data flow diagram  1. Data Flow Signifies the connectivity between various processes 2. Process   Performs some processing of input data 3. Ex

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd