Compare the productivity and difficulty, Software Engineering

Assignment Help:

Q. Compare the Productivity and difficulty?

Productivity refers to metrics as well as measures of output from production processes per unit of input. Productivity P perhaps conceived of as a metrics of the technical or engineering efficiency of production. In software project planning the productivity is defined as the number of lines of code developed per person-month

Difficulty The ratio (K/td 2) where K is software development cost as well as td is peak development time is called difficulty and denoted by D which is measured in person/year.

D= (K/td 2)

The relationship demonstrates that a project is more difficult to develop when the manpower demand is high or when the time schedule is short.

Putnam has experiential that productivity is proportional to the difficulty Pa Db


Related Discussions:- Compare the productivity and difficulty

Explain scm, What is SCM? Software Configuration Management is a set of...

What is SCM? Software Configuration Management is a set of activities carried out for identifying, organizing and controlling alters throughout the lifecycle of computer softwa

Explain equivalence partitioning, What is equivalence partitioning? Equ...

What is equivalence partitioning? Equivalence partitioning is a black box procedure that divides the input domain into classes of data. From this data test cases can be foun

Distinguish between verification and validation, Distinguish between verifi...

Distinguish between verification and validation. Verification refers to the set of activities that make sure that software correctly executes a specific function. Validation re

The roles of project stakeholders, The roles of project stakeholders :- ...

The roles of project stakeholders :- Offer resources (time, money, ...) to the project team Instruct developers about their business Be precise and specific about requir

What is change management, What is Change management? Software systems ...

What is Change management? Software systems are subject to continual change requests; From users; From developers; From market forces. Change management is

What are the task involved in design process of sdlc, What are the task inv...

What are the task involved in design process of SDLC General tasks involved in the design process are the following: i)  Design various blocks for overall system processes.

How can you create the new system, How can you create the new system  S...

How can you create the new system  System is to be computerised. Following will be created: (i)                 All DVD and CD data will be stored on a database   (ii)

What is peer reviews, What is Peer Reviews? Ans) A methodical examinatio...

What is Peer Reviews? Ans) A methodical examination of software work products by the producer's peers to recognize defects and areas where changes are required.

What is bottom-up testing, Bottom-up testing is a method of integration tes...

Bottom-up testing is a method of integration testing. A test engineer makes and uses test drivers for components that have not yet been developed, because, with bottom-up testing,

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd