Problem: Cash Flow Analysis

For the attached Gantt chart, the following information is available:

Invoices are sent at the end of each month.

Mark up is 20% on each invoice.

Invoices are paid one moth later.

The retained amount is 10% of the invoice value

All retained amounts are received 1 month after the completion of the project

Plot the cash-in and cash-out curve for the project and tabulate the amount to be financed every month.

1153_cash_flow_analysis.png

Posted Date: 7/23/2012 9:48:06 PM | Location : United States







Related Discussions:- Cash flow analysis problem, Assignment Help, Ask Question on Cash flow analysis problem, Get Answer, Expert's Help, Cash flow analysis problem Discussions

Write discussion on Cash flow analysis problem
Your posts are moderated
Related Questions
A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

There are four different commonly used financial hedging techniques and some operational hedging techniques that firms use to manage currency risk. Drawing on literature, critical


Valuation of Share A number of parties are interested however in the value of shares and securities and that will include: Company shareholders, vendors and directors of

Factors Affecting Share Prices The entire sorts of influences affect share prices. These influences involves as: 1. The current profit record of the company particularly th

Advantage of Leasing an Asset 1. The company has the choice to purchase assets on the expiry of the lease period at that time it will identify the viability of the asset

Constant amount per share or fixed D.P.S. 1. The DPS is fixed in total amount of irrespective of the earnings level. These generate certainty and are consequently preferred vi

Present Value Concept - Discounted Cash Flow Techniques This perception acknowledges the fact which a shilling losses value along with time and as that if it is to be compared

A City has determined that building a new water distribution system using a new source of water would have an annual costs of $5,750,000 and annual net benefits of $4,250,000. The

ascascasc