Calculate the total variable cost of 6,400 units product, Cost Accounting

Assignment Help:

A company has developed a new product which it will launch next month. During the initial production phase the company expects to produce 6,400 units in batches of 100 units. The first batch to be produced is expected to require 25 hours of direct labour. The following details are expected to apply throughout the initial production phase:

•  Direct material cost per unit is expected to be $4  
•  Direct labour is to be paid $10 per hour  
•  A 90% learning curve is expected to apply  
•  Other variable costs are expected to be $2 per unit 

(a)  Calculate the total variable cost of the 6,400 units of the new product.

 
(a)
  $
Direct material (6,400 units x $4)                                         25,600
Direct labour (see below)                                                       8,503
Other variable costs (6,400 units x $2)                                12,800
                                                                                             46,903
 
Direct labour:
 
The time taken is expected to be:
 
 Y=axb = 25 x 64 -0.1520   = 13.286 hours per batch, which is a total of 850.32 hours for 64 batches
 
 850.32 hours x $10 per hour = $8,503.20

 


Related Discussions:- Calculate the total variable cost of 6,400 units product

Prepare the draft sfp for the fiscal year, Prime Essentials Limited is a sm...

Prime Essentials Limited is a small private corporation. The owner plans to approach the bank for an additional loan or a line of credit to facilitate expansion. The company bookke

Estimate the required rate of return, a)     Company X is expected to maint...

a)     Company X is expected to maintain a constant 7% growth rate in their dividends, indefinitely. If the company has a dividend yield of 4%, what is the required return on their

Calculate the tax base of the interest received, Prepare answers to each of...

Prepare answers to each of the following questions.  Assume a tax rate of 30%. (i) Harry Ltd has a balance of prepaid rent in the balance sheet amounting to $100 000 as at 30 Ju

Calculation of deductions - wages department, Calculation of Deductions - W...

Calculation of Deductions - Wages Department A range of deductions are complete from gross earnings when computing the net payment because of the employee, that deductions may

Features of jit, What are the major features of JIT?

What are the major features of JIT?

Direct labour rate variance, Direct Labour Rate Variance It is the dif...

Direct Labour Rate Variance It is the difference among the actual direct labour rate and the standard direct labour rate for the total hours worked. Utilizing an equation,

Statements on tax standards, Compare the American Institute of CPAs' (AICPA...

Compare the American Institute of CPAs' (AICPA) Statements on Tax Standards (SSTS) and the Treasury Department Circular 230 rules to practice before the Internal Revenue Service (I

Marginal costings, how marginal cost of a product is determined?

how marginal cost of a product is determined?

Explain stock valuation, G. Mills was appointed a local agent for the High ...

G. Mills was appointed a local agent for the High Power Mobile Workshop Bolt (HPMW-B) on 1 April 2009. The HPMW-B is manufactured by Mobile Equipment Ltd (MEL). The company charges

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd