Calculate the number of paths and critical paths, Civil Engineering

Assignment Help:

Calculate the Number of Paths, Number of Critical Paths and Project Duration

For the project network shown, the total number of paths through the network; number of critical paths; and, project duration (days) is most nearly:

a. 6; 2; and, 26 

b. 6; 1; and, 26 

c. 5; 1; and, 25

d. 3; 3; and, 24

539_Calculate the Number of Paths, Number of Critical Paths and Project Duration.png

Solution:  List the number of paths and calculate the duration for each.  

L M O R T V   = 4 + 7 + 2 + 2 + 2 + 9 = 26-days -- Critical

L M O S U     = 4 + 7 + 2 + 3 + 7 = 23-days

L M Q V      = 4 + 7 + 6 + 9 = 26-days - Critical 

L M Q U    = 4 + 7 + 6 + 7 = 24-days

L N P Q U    = 4 + 3 + 6 + 7 = 20-days

L N P Q V    = 4 + 3 + 3 + 6 + 9 = 25-days


Related Discussions:- Calculate the number of paths and critical paths

Probable distribution function, The diameter of an electric cable, say X, i...

The diameter of an electric cable, say X, is assumed to be continous random variable with pdf;f(x)=6x(1-x), 0 b}.

Maintenance of drainage and shoulders, Maintenance of Drainage: Maint...

Maintenance of Drainage: Maintenance of drainage will ensure that the run-off is taken away from the runway efficiently. The side ditches and buried pipes should be cleaned r

Define the predominant factor in atmospheric corrosion, Define the Predomin...

Define the Predominant factor in atmospheric corrosion? The predominant factor in atmospheric corrosion in areas located above splash zone is moisture as there is an excess ava

Angle measurment, calculating included angle and bearing

calculating included angle and bearing

Mechanism of plastic settlement in fresh concrete, Q. Mechanism of plastic ...

Q. Mechanism of plastic settlement in fresh concrete? Within a few hours after placing of fresh concrete, plastic concrete can experience cracking due to occurrence of plastic

Define project scheduling - types of methods, Define Project Scheduling - T...

Define Project Scheduling - Types of Methods Project Scheduling - Distinction between the Major Types of Schedule Diagrams Precedence Diagrams (PDM)   a) Activ

Geometric design, calculating OVERTAKING SIGHT DISTANCE

calculating OVERTAKING SIGHT DISTANCE

Define the planning an underwater inspection, Define the Planning an Underw...

Define the Planning an Underwater Inspection? Planning for underwater inspection is important because of - Unknown factors which may be discovered during the diving - Th

Show the excessive movement joints in bridges, Q. Show the Excessive moveme...

Q. Show the Excessive movement joints in bridges? Movement joints are generally added to bridge structures to accommodate movements because of dimensional changes arising from

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd