Calculate the number of paths and critical paths, Civil Engineering

Assignment Help:

Calculate the Number of Paths, Number of Critical Paths and Project Duration

For the project network shown, the total number of paths through the network; number of critical paths; and, project duration (days) is most nearly:

a. 6; 2; and, 26 

b. 6; 1; and, 26 

c. 5; 1; and, 25

d. 3; 3; and, 24

539_Calculate the Number of Paths, Number of Critical Paths and Project Duration.png

Solution:  List the number of paths and calculate the duration for each.  

L M O R T V   = 4 + 7 + 2 + 2 + 2 + 9 = 26-days -- Critical

L M O S U     = 4 + 7 + 2 + 3 + 7 = 23-days

L M Q V      = 4 + 7 + 6 + 9 = 26-days - Critical 

L M Q U    = 4 + 7 + 6 + 7 = 24-days

L N P Q U    = 4 + 3 + 6 + 7 = 20-days

L N P Q V    = 4 + 3 + 3 + 6 + 9 = 25-days


Related Discussions:- Calculate the number of paths and critical paths

Lagrange''s mean value theorem, Write some appplications of lagrange''s mea...

Write some appplications of lagrange''s mean value thorem

Why are steel plates inserted inside bearings, In designing of elastomeric ...

In designing of elastomeric bearings, why are steel plates inserted inside Bearings?

Soil in road construction, Soil in Road Construction: Road Embankme...

Soil in Road Construction: Road Embankment and Sub-grade Soil is mainly used as the material for constructing a road embankment. The road embankment supports the road

Surveying, What is reciprocal ranging

What is reciprocal ranging

Storm water, what are the roles of civil engineers in storm water managemen...

what are the roles of civil engineers in storm water management

Manufacturing technique of ferro cement, what are the manufacturing techniq...

what are the manufacturing techniques of ferro cement?

Sub-base for concrete carriageway - non-strength provider, Sub-base for con...

Sub-base for concrete carriageway - non-strength provider Essentially sub-base for a concrete carriageway is provided for the below reasons: (i)  It provides aneven and smo

Example of magnetic dip, Example : Line AB was drawn with a magnetic ...

Example : Line AB was drawn with a magnetic bearing of 136° 45′ while the magnetic declination was 2° 30′ east In an old map. If magnetic declination is 3° 30′ west to what m

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd