Areas of risk and causes of risk, Other Management

Areas of risk and causes of risk

Below are mentioned few areas and causes of risk. The term „operator? used in this listing means the owner (you) who awards the contract to the contractor. The areas mentioned need attention in the contract that you prepare for the project.

Contractual risks: The risks are:

  • Operator group and contractor group property and personnel: The contract should define the costs of loss of or damage to the parties.
  • Project works including both operator and contractor supplied items: The contract should define the responsibility for loss of or damage to the project works.
  • Pollution: The contract should define responsibility for the effects of pollution and contamination emanating from the contractor groups.
  • Third parties: The contract should define the legal liability for third parties? losses caused by each including in circumstances where a contractor is required to perform work in an area of close proximity to any existing facilities.
  • Consequential losses: The contract should define the indemnities for each party?s group?s respective indirect or consequential losses howsoever caused or arising (including negligence) - whether or not foreseeable at the date of the contract.
  • Warranty    obligations:    The    contract   should    define   warranty obligations  and defective performance liabilities    in    terms    of magnitude, time and remedy.
  • Unlimited liability/damages at large: The contract should define or limit the contractor group?s total cumulative liability to enable him to assess his overall exposure resulting from, for example, liability for delay, damage, rework, re-performance and so on.
  • Insurance  cover:  The  contract  should  define  full  details  of  the insurance policy terms, conditions, limits and exclusions.
  • Force majeure and suspension: The contract should define the rights for both parties, if the condition exceed a specified time because of force Majeure.
  • Delay: The contract should define contractor?s liability for delay and
  • liquidated damages both under contract and at law.
  • Variation  orders:  The  contract  should  define  the  contractor?s obligations to perform the variation orders taking into account other existing commitments.
  • Access to worksite: The contract should define the access to the work site and remedies as a result of restricted access to the work site by the operator or any party
  • Intellectual property (IP) rights: The IP rights in terms of the party who  developed  those  IP  before  or  during  the  project  should  be clearly identified.
  • Termination   by   operator   for   convenience:   If   the   operator terminates the whole or part of the work for his convenience then the contract should define the entitlement to payment for all work performed, materials including cancellation costs relating thereto and termination fee.
  • Operator's obligation to pay contractor: Payment by the operator to the contractor is a material term of the contract and time critical.

Performance risks: The risks are:

Scope, nature and duration of work: This includes:

  • Lack of clear definition of scope, nature and duration of work in bid document.
  • Insufficient time given to bidding contractors to understand and quote.
  • Wrong information in bid document.
  • Scope outside the bidding contractor?s knowledge.
  • Schedule  interactions:  This  includes  owner  initiated  schedule changes and contractor initiated schedule changes.
  • Size: Large size of contract increases chance of the above two risks.
  • Safety and  environmental  performance:  Operator  and  industry safety performance targets not defined in bid.
  • Weather: If contractor is able to absorb this risk up to a limit, the contract should specify this limit.
  • Soil and foundations: Risk cannot be fully measured by contractor prior to commencement of work. Hence risk should be generally borne by owner.

External influences: Risks which are outside contractor's control like:              

  •     Access.
  •     Interfaces with owner and other contractors.
  •     Politics.
  •     Risks of interference and disturbance.

Owner and influences at time of bid: This includes:

  •   Incomplete information at time of bid.
  •   Contract being re-bid or renegotiated over an extended period of time leads to lack of continuity in the bid process and amongst personnel and these impact negatively on contractor?s performance.

Financial risks: Risk that needs attention in the area is the profitability, value of contract - size, balance sheet debt, off balance sheet debt, level of exposure, foreign currency exposure, terms of payment, owner creditworthiness and insurance.
Political risks: Risk that needs attention in the area is the interference by government, local disturbance, breach of confidentiality, delay in permits and licenses.
Technical risks: Risk that needs attention in the area is the quality of Front End Engineering Design (FEED) and understanding new technology.
Geographical risks: Risk that needs attention in the area is the location of the work, weather and soil and foundations.
Operator risks: Risk that needs attention in the area is the operator areas of influence, insurance and problems which impact the operator can impact the contractor.

Posted Date: 9/28/2012 2:45:25 AM | Location : United States







Related Discussions:- Areas of risk and causes of risk, Assignment Help, Ask Question on Areas of risk and causes of risk, Get Answer, Expert's Help, Areas of risk and causes of risk Discussions

Write discussion on Areas of risk and causes of risk
Your posts are moderated
Related Questions
Arrangement of Entries   The actual process of filing starts when sufficient number of cards accumulate.  Preliminary arrangement  In the preliminary arrangement we sor


Shelf Register/Shelf List: Shelf register or shelf list is an important record of books; which shows the position of any book on the shelves. In order to control the movement


P roject quality management process Project quality management consists of four main processes: Quality Definition. Quality Assurance. Quality Control. Qua

QUESTION CASE STUDY Tesco began in 1919 with one man, Jack Cohen, a market stallholder selling groceries in London. TESCO was formed out of a merger with T.E. Stockwell f

a) Define "news" and illustrate the concept of "news worthiness" in the field of PR. b) Describe how PR is distinguished from i. Advertising ii. Marketing iii. Sales pr

Question : (i) Give two reasons why fish could be aggregating around a floating object. (ii) What are the differences between (a) an anchored fish aggregating device; (b)

Library Networks in USA and UK   The United States has definitely taken a lead in library networking. Among the prominent agencies in this regard, are the Library of Congress,

QUESTION a) Define risk as per the Public Private Partnership Guidance Manual b) What are the primary objectives of transferring risks from a contracting authority to a priv