[Production Capacity] Consider the following process. Every traveler from Vancouver to the U.S. has to pass security and then immigration at Vancouver. There are 4 security lanes/counters and 10 immigration counters. It takes 1 minute for a security lane to process a traveler (not including waiting time). It takes 3 minutes for an immigration agent to process a traveler. These counters open at 5 a.m.
1. You arrive at 5 a.m. to security, when do you expect to complete immigration?
2. A group of 6 students arrives at 5 a.m. to security. When will all of them complete immigration? (All processing is done individually and not in groups.)
3. How many travelers per hour can this system handle if it operates non-stop, 24/7?
4. If we had the budget to add one more agent, should we add a security agent or an immigration agent? How many travelers can the system handle per hour now?
5. Back to 4 security agents and 10 immigration agents. Assume now that for group travelers, all members are served simultaneously by one immigration agent (security is done individually). Immigration processing time per group = 2 minutes + 1 minute for each passenger. If most travelers are individual, which agent-type do we need more of to increase capacity? If most travelers are in groups of 4, which agent-type do we need more of to increase capacity?
What is a work breakdown structure
: What is a work breakdown structure (WBS) and how is it used? What information is needed before a project team can create a WBS? Consider a simple or common task. What are the summary tasks and work packages? What are some ways that you may want ..
|
Explain the contribution of cultural sensitivity
: Explain how cultural factors, including values, influence leadership practice. Explain the contribution of cultural sensitivity and cultural intelligence to leadership effectiveness
|
Breaking down the scope of a project
: The WBS process is about breaking down the scope of a project. Therefore, what input is needed before starting a WBS? Also, how detailed / granular do you want to get in your WBS creation and why? How does the size and complexity of a project a..
|
Difference in gender proportions that favored commercial a
: Give an estimate of the difference in gender proportions that favored Commercial A. Also construct a large-sample 95% confidence interval for this difference.
|
When do you expect to complete immigration
: Consider the following process. Every traveler from Vancouver to the U.S. has to pass security and then immigration at Vancouver. There are 4 security lanes/counters and 10 immigration counters. How many travelers per hour can this system handle if i..
|
Discuss expected findings and ways to improve the program
: Discuss expected findings and ways to improve the program you evaluated. Discuss ways you plan to apply what you learned in this course and in developing the evaluation plan in your current or future position.
|
How you will address jim recent performance issues
: Write a one (1) page paper in which you: Explain how you will address Jim's recent performance issues. Suggest both constructive and positive feedback designed so that Jim will leave motivated to do his best
|
Determining the decertification elections
: Why are employers becoming more interested in decertification elections? What role does the union play in decertification? What role does management play in the decertification process?
|
Marketer is reviewing a series of research reports
: A marketer is reviewing a series of research reports that were generated six months ago, 12 months ago and 18 months ago to determine the levels of brand awareness among a particular customers group. The marketer is considering commissioning a new st..
|