What is the critical path for this network

Assignment Help Operation Management
Reference no: EM131148860

Hamilton County Parks is planning to develop a new park and recreational area on a re- cently purchased 100-acre tract. Project development activities include clearing play- ground and picnic areas, constructing roads, constructing a shelter house, purchasing picnic equipment, and so on. The following network and activity times (in weeks) are being used in the planning, scheduling, and controlling of this project:

Activity A B C D E F G H I

Time    9 6 6 3  0  3 2 6 3

a. What is the critical path for this network?

b. Show the activity schedule for this project.

c. The park commissioner would like to open the park to the public within six months from the time the work on the project is started. Does this opening date appear to be feasible? Explain.

Reference no: EM131148860

Questions Cloud

What obvious symptom would this drug produce : How would this affect neural transmission along the axon in these neurons, and what obvious symptom would this drug produce
How metrics such as valuation economic profit : Demonstrate how metrics such as valuation, economic profit, and related terms are measured and evaluated. Explain the significance and implications of various economic theories pertaining to profit.
How nonverbal communication is played out in society : What is an example of how nonverbal communication is played out in society (provide links if possible)? Are there campaigns/movements/etc working to bring attention to these types of issues
How total quality management principle and tools can be used : describe how total quality management principles and tools can be used to improve quality in the latest line of products in the context of the Nissan case study.
What is the critical path for this network : Hamilton County Parks is planning to develop a new park and recreational area on a re- cently purchased 100-acre tract. Project development activities include clearing play- ground and picnic areas, constructing roads, constructing a shelter house, p..
Is learning forgotten once extinction happens : Operant conditioning often evokes strong opinions. Some believe that true learning does not occur because the individual is dependent on tangible rewards. Is learning "really" occurring, or is it only dependent on consequence? Is learning "forgotte..
Complete the partial income statement if the company paid : Complete the partial income statement if the company paid interest expense of $18,000 for 2011 and had an overall tax rate of 40% for2011.
Compute implications for each of the computed elasticities : Determine the implications for each of the computed elasticities for the business in terms of short-term and long-term pricing strategies. Provide a rationale in which you cite your results.

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd