What is the amount of the total fixed costs
Course:- Project Management
Reference No.:- EM1343571





Expertsmind Rated 4.9 / 5 based on 47215 reviews.
Review Site
Assignment Help >> Project Management

Production level of 5,600 units a project has total costs of $89,000.

At a production level of 5,600 units a project has total costs of $89,000. The variable cost per unit is $11.20. What is the amount of the total fixed costs if the production level is increased to 6,100 units without increasing the total fixed assets?




Put your comment
 
Minimize


Ask Question & Get Answers from Experts
Browse some more (Project Management) Materials
How can a transformational experience influence you as a leader and manager and what skills can you acquire from a transformational experience or critical incident?
Research should be from scholarly, peer-reviewed sources.Prepare this assignment according to the APA guidelines found in the APA Style Guide, located in the Student Success C
Identify risk drivers in your project and the risks associated with each and explain how the risks you identified could impact the project, and propose strategies to mitigate
In the final project, you play the role of a project manager for Riordan Manufacturing. The vice president of international operations has hired you to oversee the relocation
Identify which process improvement tool or technique you will included in your overall project plan. Explain in detail how this will be implemented and what benefits or improv
In 250 words, find a contemporary article showing how the theory of psychological egoism in a corporation resulted in an ethical dilemma. Is there a way that the decision-m
Select a recent issue of Fortune, Fast Company, BusinessWeek, or another business periodical approved. - Select an article that will appeal to them and that you can relate to
Identify how project management improves the success of information technology projects - Explain the relationship of the scope of a project to the work breakdown structure.