Problem
A. The Harvey motorcycle company produces three models: the Tiger, a sure-footed dire bike; the LX2000, a nimble café racer; and the Golden, a large interstate tourer. This month's master production schedule calls for the production of 54 Goldens, 42 LX2000s, and 30 Tigers per seven-hour shift.
a. What average cycle time is required for the assembly line to achieve the production quota in seven hours?
b. If mixed-model scheduled is used, how many of each model will be produced before the production cycle is repeated?
c. Determine a satisfactory production sequence for the ultimate in small-lot production: one unit.
d. The design of a new model, the Cheetah includes features from the Tiger, LX2000, and Golden models. The resulting blended design has an indecisive character and is expected to attract some sales from the other models. Determine a mixed-model schedule resulting in 52 Goldens, 39 LX2000s, 26 Tigers, and 13 Cheetahs per seven hour shift.

B. A company using a Kanban system has an inefficient machine group. For example, the daily demand for part L105A is 3,000 units. The average waiting time for a container of parts is 0.8 day. The processing time for a container of L105A is 0.2 day, and a container holds 270 units. Currently, there are 20 containers for this item?
a. What is the value of the policy variable representing the safety stock percentage?
b. What is the total planned inventory (work in process and finished goods) for item L105A?
c. Suppose the safety stock percentage was 0 (zero). How many containers would be needed now? What is the effect of the safety stock percentage in this example?

 

Reference no: EM13215222

Questions Cloud

The optimal order quantity : A mail-order house uses 18,000 boxes a year. Carrying costs are 60 cents per box a year, and ordering costs are $96. The following price schedule applies - The optimal order quantity.
Create your own function that accepts one input parameter : Using Pseudocode, create your own function that accepts one input parameter and returns a float number. You decide the theme.
Graph the system of inequalities : Graph the system of inequalities: X1 + X2 ≥ 3, 3X2 ≤ 9, 2X1 ≤ 10, X1 ≥ 0, X2 ≥ 0. Which of the following statements is true?
How engineers estimate that the facility will remain useful : Water Planet is considering purchasing a water park in Atlanta, Georgia, for $1,870,000. The new facility will generate annual net cash inflows of $460,000 for eight years. Engineers estimate that the facility will remain useful for eight years an..
What average cycle time is required for the assembly line : What average cycle time is required for the assembly line to achieve the production quota in seven hours-If mixed-model scheduled is used, how many of each model will be produced before the production cycle is repeated?
Write a gui-based program that analyzes a round of golf : Write a GUI-based program that analyzes a round of golf. You will retrieve the data for 18 holes from a text file. On each line in the file will be the par for that hole (3, 4, or 5) and your core for that hole should be displayed in a label. Prov..
Explain what would be the amount of the equity : Based on your answer in (c), what would be the amount of the equity up front that you would have to give up in order to obtain LipLife's original venture capital investment?
Hat does mbsa do to check for weak local account passwords : hat does MBSA do to check for weak local account passwords?
Clarify the difference between vulnerabilities and threats : Summarize the primary vulnerabilities and potential threats that exist for GITI related to the practice of storing sensitive data on laptops. Use your answer to clarify the difference between vulnerabilities and threats.

Reviews

Write a Review

 

Operation Management Questions & Answers

  The reorder point is defined as the lead time demand

The reorder point is defined as the lead time demand for an item. In cases of long lead times, the lead time demand and thus the reorder point may exceed the economic order quantity

  Work for an international clothing companu called armoni

you work for an international clothing companu called.Armoni. A non-profit organization has just revealed that a line of your stonewashed jeans is produced in hazardous conditions in bangladesh.

  Data is planning to make his monthly trek

Lieutenant Commander Data is planning to make his monthly (every 30 days) trek to Gamma Hydra City to pick up a supply of isolinear chips. The trip will take Data about two days.

  Implications of price wars for a company

Under what environmental conditions are price wars most likely to occur in an industry? What are the implications of price wars for a company?

  Relations be renormalized to form physical

List three common situations that suggest that relations be renormalized to form physical records.

  National origin discrimination

National origin discrimination is prohibited against a job applicant or employee. Besides discriminating against the job applicant or employee directly.

  Write a brief explaining strengths and weaknesses of both

You would like to set up a Web site to sell towels, linens, pottery and tableware from Portugal and are examining services for hosting small business Internet storefronts. Write a brief report indicating your choice and explaining strengths and wea..

  Elucidate what present issues in these global locations

Thought an American based organization needs to take into account when working in multiple nations with vastly different employment laws. Elucidate what present issues in these global locations may affect success of an American based organization.

  How mission and vision influence organizational design

How might mission and vision influence organizational design? Why are mission and vision relevant to the management of internal organizational social networks?

  Explain the relationship between custom and standard goods

Explain the relationship between custom, option and standard goods and services as they relate to project, job shop, flow shop and continuous flow processes.

  Illustrate what is number of late jobs

A single machine work center has 5jobs assigned to it. Using first-come-first-served priority rule, illustrate what is number of late (tardy) jobs.

  External competitiveness from policies on internal alignment

Distinguish policies on external competitiveness from policies on internal alignment. Why is external competitiveness so important? What factors shape an organization's external competitiveness?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd