Preparing the project risk-management plan

Assignment Help Project Management
Reference no: EM13978806

You are preparing the project risk-management plan for review with the sponsor and your manager. You have identified the risks, assessed the probabilities and impacts, and created your responses. You now need to present the comprehensive plan and gain the buy-in from the sponsor on the risk-management plan.

Individual Guidelines:

• Create risk responses (reduce probability, reduce impact, and respond) for each of the 15 risks you identified and assessed in the prior unit.

• Use either Word or Excel to record this information

Types of risk involved in the project

1. the first risk involved deals with marshaling the manpower for the project in time. This is a schedule risk. This risk exists because the project is to be handled exclusively by internal manpower.

2. the second risk is that of completing thee milestones of the project in time. This is a schedule risk. Since this product is new a risk exists that there may be aspects of the project which may have been overlooked..

3. the budget estimates may need to be revised. This is a budget risk.

4. there may be a problem with the contractors brought in to consult on the production process. This is a business risk.

5. the production of this product is also new for the company. This is a business risk ass it is unchartered waters for the company.

6. employees working on this project will be forced to massively multitasks a number of projects at thee same time. This is a technical environment risk.

7. the fact that the product will be produced internally also poses a new challenge to the company as this is a first. This is a technical environment risk.

8. the person chosen to lead the process has not led any projects since joining the company. This is a technical environment risk.

9. the decision of the project leader came as a surprise to the person chosen as a project leader. This surprise is due to the fact that inadequate notice was not given to the chosen project leader. This is a technical environment risk.

10. the project manager has not worked with any of the people outside the engineering department and barely knows them. This is a technical environment risk.

11. the market has not been effectively analyzed before the onset of this project. This presents a programmatic risk.

12. something might go wrong during the manufacturing process. This is an operational risk.

13. since the product is to be released in a field that is highly regulated by the government there may be a lot of constraints placed on the product. This is a business risk.

14 the consumers might reject this product due to its untested nature in the business field. This is a business environment risk.

15. the quality manager position is still vacant. This is an internal environment risk. This is a critical role and the project cannot begin without this role being occupied.

Reference no: EM13978806

Questions Cloud

The financial plan is : The financial plan is:
Portfolio of non-dividend-paying stocks earned geometric : A portfolio of non-dividend-paying stocks earned a geometric mean return of 5 percent between January 1, 2004, and December 31, 2010. The arithmetic mean re- turn for the same period was 6 percent. If the market value of the portfolio at the beginnin..
Prioritize the leadership tasks during an emergency : From the e-Activity, give your opinion on how well your selected leader performed leadership tasks and response to the disaster or crisis during the emergency situation. Provide a rationale for your response.
Determine the electric field half way between two charges : Draw a representative set of electric field lines for the system and determine the electric field half way between the two charges.
Preparing the project risk-management plan : You are preparing the project risk-management plan for review with the sponsor and your manager. You have identified the risks, assessed the probabilities and impacts, and created your responses. You now need to present the comprehensive plan and ..
Find the magnitude of the force per unit length on each wire : Two parallel wires with centers separated by 8.2mm each carry 15A in the same direction. Find the magnitude of the force per unit length on each wire. Find the direction of the force per unit length on each wire.
Retained earnings amount on this years balance sheet : Bigco’s balance sheet one year ago indicated retained earnings of $448.7million. This year, Bigco’s net income was $36 million. It paid its preferred shareholders a dividend of $5.4 million and its common shareholders a regular dividend of $5.7 milli..
Who is your representative to the california assembly : Who is your representative to the California Senate? (include a link to their website) How long have they been in office? What is their party affiliation
Compute the magnitude and direction of the electric field : When each sheet has a uniform surface charge density Sigma = + 2.4 nC/m2, determine the magnitude and direction of the electric field in region I, to the left of the left-most sheet.

Reviews

Write a Review

Project Management Questions & Answers

  Determined the actual number of workstations

You have just determined the actual number of workstations that will be used on an assembly line to be 8 using the assembly-line balancing procedure

  Gross profit margins are expected to average about 30

gross profit margins are expected to average about 30 percent each year. because of relatively high marketing

  Compute the growth duration of each company stock

Compute the growth duration of each company stock relative to the S&P Industrials, compute the growth duration of Company A relative to Company B and what determines your investment decision?

  Construct a network diagram and find the critical path

Evaluate the scheduled completion time and identify the critical path and what is the slack time (float) for activities A, D, E, and G

  Describing a project with initial cash outlay

The information below describes a project with an initial cash outlay of $10,000 and a required return of 12%.

  Explain elements of project management plan

I have the following task, and I need some help getting started: Write a 900-1,400-word paper explaining the elements of a project management plan for implementation and ongoing use of a knowledge management system.

  Create a fictional information technology project include

Create a fictional information technology project include: a project charter,requirement documents, WBS, schedules, staffing plans, budgets, risk management plans, communication -plans, change management plans based on text Information Technology pro..

  Hr manager and characteristics

Analyze how HR can be used effectively to work cohesively with an organization's business strategy and explain what steps you could take to ensure flawless execution.

  Calculate the npv of the project

Calculate the after tax cash flows for the project for each year. Explain the methods used in your calculations. If the discount rate were 6 percent calculate the NPV of the project. Is this an economically acceptable project to undertake. Why or w..

  Concentrate this modules area of research on microsofts

concentrate this modules area of research on microsofts risk management approach. write a 1-2 pages apa style paper

  Logos pathos ethos and credibility for communicationsound

logos pathos ethos and credibility for communicationsound leadership is received through verbal and non-verbal

  Calculate schedule variance and schedule performance index

Calculate the schedule variance, schedule performance index, and cost (actually value in this case) performance index. How is the project going?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd