Prepare and construct a gantt chart using the information

Assignment Help Project Management
Reference no: EM131412025

Project Management

SECTION A -

This ECA case is designed to allow students to apply the materials learned from the course. Students are encouraged to use Microsoft Project software for this assessment.

Please note that the details of this project are fictitious. Any resemblance to real life situations is purely coincidental.

PROJECT CASE: Skill Future Course Development Background

As Singapore economy matures and education Ievel increases, having a tertiary education does not guarantee Singaporeans employment. In fact there is a gap between job requirements and academic qualifications. Companies are looking for people who possess skills to solve problems. Hence government promotes life-long earning. Skills Future is established to develop an integrated, high-quality system of education and training that responds to constantly evolving industry needs. Citizens are given support to upgrade their skills and mastery.

Digital Science Institute (DSI) is a private education centre providing Engineering and IT trainings. With government's launch of Skills Future, DSI sees an opportunity to conduct more technical courses on the latest technologies. As many companies require fast prototype developments, 3D Printing will be a grow area There is a potential demand for 3D Printing courses which trainees can pay for with their Skills Future fund. DSI has proposed to the Workforce Development Agency (WDA) and apply for funding to set up a 3D Printing Course and Lab. DSI management call it the 3D Printing (3DP) Project.

Section 1: Managing the Project Team

Assuming you are DSI's Head of Program (HOP) for Manufacturing Courses. There is no strong knowledge in 3D Printing in your department yet.

On 1 Sep 2016, the CEO, M r. Alan Tan, appointed you to head the 3DP Project. He wants the project to start on 1 Nov 2016. The course must be launched on 3 Jan 2017, the first day of the new academic year. WDA will fund only part of the project cost. Hence, CEO wants you to minimise the project cost where possible. As a start, basic 3D Printing theories and practical lessons must be conducted. Any expansion of the syllabus can be done in future runs.

Question 1

(a) To reflect on the CEO's directions, appraise the priority of the project and construct a project priority matrix.

(b) You are asked to form the project team by recruiting members either internally or externally. Analyze and discuss three (3) personal attributes (excluding technical expertise) of team members that are most critical to the success of this project.

Section 2: Developing a Project Plan

After some searching, the following members are recruited to the project team:

(i) Yourself: Project Manager.

(ii) Mr. John Harvey: A 3D Printing academia hired from an overseas research institute.

(iii) Ms. Roshida: DSI's Lab Manager.

(iv) Ms Jessy Ang: DSI's Purchasing Officer.

You conducted a pre project discussion with your team members. The team worked out the project activities and preliminary details as shown in Table 1.

Table 1: Activities List for 3D Printing (3DP) Project

Activity Number

Description

Duration

Prede­cessors

Resource

1

3D Printing (3DP) Project




2

Project kick off meeting

1 day


PM

3

Requirement studies

5 days

2

John

4

Course development

21 days

3

John

5

Recruit instructors

15 days

3

PM

6

Purchase 3D printers

14 days

3

Jessy, 3D Printers

7

Purchase workstations

7 days

3

Jessy,Workstations

8

Lay electrical cables

5 days

3

Roshida, Electrical Cables

9

Lay network cables

5 days

8

Roshida, Network Cables

10

Setup workstations

8 days

7,9

Roshida

11

Install 3D printers

7 days

6,10

Roshida

12

Test overall system

4 days

10,11

Roshida

13

Print course material

8 days

4

John, Course
Materials

14

Apply Ski I I sFuture status

6 days

4,5

PM

15

Administer students' applications

5 days

14

PM

16

Promote to i ndustry

7 days

14

PM

17

Setup online portal

5 days

13

John

18

Standby and support

3 days

19FF

Roshida

19

Launch course

1 day

12,13,15,16,17

PM

A budgetary costing would have to be reported for approval. The unit costings are shown in Table 2 and 3:

Table 2: Hourly rates for staff cost

Resource Name

Cost (Week day rate)

PM

$50/hr

John

$55/hr

Roshida

$45/hr

Jessy

$40/hr

The following resource costs can be treated as material costs for relevant activities

Table 3: Material/Ad-hoc Item Cost

Resource Name

Material/Item Cost

3D Printers (1 lot)

$24,000

Workstations (1 lot)

$12,000

Electrical Cable (1 lot)

$1,500

Network Cable (1 lot)

$1,000

Course Materials (1 lot)

$1,000

Ad-hoc Admin Staff

* $450 per day (for week days)

Temp Engineer

* $360 per day (for week days)

Note on the costs:

1. The Saturday, Sunday and Public Holiday (PH) and Leave-In-Lieu rates for Project Team members and Ad-hoc staff are two times that of normal week day.

2. As the project will be partly fund by WDA (percentage of funding will be decided by WDA), you have to present the project cost to your management. Hence all related staff costs involved in this project shall be treated as variable costs calculated based on the number of days each staff works on the project.

3. The ad-hoc Admin Staff, internally from DSI, is to be deployed by pulling staff out from other lower priority projects. The Temp Engineer is to be contracted from an outsourcing company. Their costs are to be calculated based on actual durations needed, and added to the related activities costs.

Note on using MS Project for Q2 &3:

1. The above schedule and costing are based on a 5-day work-week. Each day has 8 working hours. No work will be performed on Saturday, Sunday and public holidays unless otherwise stated or you deem necessary. Do not change any durations predecessor relationships or the resources assignments unless you can justify with good reasons to do so.

2. The relevant public holidays which may fall into the project period are Christmas on 25 Dec 2016 and New Year on 1 Jan 2017. If a Public Holiday falls on Sunday, the next day (Monday) will be a Leave-in-lieu. No I eave-in-lieu for Public Holiday on Saturday. You have to mark in MS Project all Public Holidays and Leave-in-lieu as Non-Working Days (Project-> Change Working Time).

3. Click View->Gantt Chart (Leftmost icon)->More View->Resource Sheet to enter the name, type and cost of each resource item into the Resource Sheet.

4. Click View->Gantt Chart4 Gantt Chart, then View->Table->Entry to enter the Task Name, Duration, Predecessors and Resource in the Gantt Chart Entry Table View. Do not change the order of the activities (you are not required to rearrange the list according to WBS).

Set Activity 1 as the Higher Level Activity by highlighting all activities before and right indent them to second level.

Then Click Project -> Project Information -> Set Start Date as directed by CEO.

Right click on Activity 19 Launch Course to access its Information; Under Advanced Tab, Set Constraint Type as "Must Start On", set Constraint Date as the date directed by the CEO.

5. To see any resource conflicts, select all task, right click to choose Auto Schedule, then Resource Tab ->CI ear Levelling. Observe any resource conflicts.

6. Diagrams, charts, tables, graphs and relevant project outputs may be shown as images in Q2 & 3. These must be appropriately formatted and presented so that they are legible and can be comfortably viewed.

Question 2

(a) Prepare and construct a Gantt Chart using the information and steps outlined above before resolving any resource conflicts. Present the MS Project Gantt Chart View with columns for Information (i), Task Name, Duration, Start Date, Finish Date, Predecessors and Resource Names clearly shown. Determine the Project Finish Date (Activity 1)

(b) Determine the total project cost before resolving the resource conflicts. Present the information with a MS Project cost table or report.

(c) Examine any resource conflicts and activities delayed. Identify the activities and resources involved.

(d) Evaluate the most cost effective way to resolve each conflict without sacrificing other priorities. You may use Auto Resource Leveling feature of M S Project (see note below), but you must explain what the levelling has done.

If the conflict cannot be resolved through Auto Resource Leveling, appraise two options for accelerating project completion when resources are not constrained, bearing in mind that the core team has already been formed, the members' pace cannot be quicken further and the task cannot be transferred to other members with different skills.

For each option, evaluate the impact on cost then choose the best option. Explain any changes you make to the project.

Note: To Level Resource, do the followings:

Click Resource-> Levelling Option -> check the Level button, click on Level Entire Project, then uncheck the box: Level only within available slack. Finally click Level All. Then click Skip for activities that cannot be levelled.

After resolving the conflicts and schedule issues, you made the necessary schedule and cost changes to the M S Project File. The CEO approved the changes.

Set the status date (Project->Status Date) as 2 Nov 2016. Then set the baseline in MS Project (Project->Set Baseline- Entire Project). The project proceeds on.

Section 3: Tracking a Project

During the implementation period, the following issues emerge:

i. The 3D printers cost increased by 5% due to the appreciation of US Dollar.

ii. The 3D printers initially cannot be interfaced with the workstations. Test overall system (Activity 12) requires three additional days to solve the problem.

iii. The network cabling routing paths has to be redesigned due to some obstruction in the building structure. The cost of Network Cables increased by $600 due to additional cables required. There is no change in the schedule.

Question 3 -

You are required to carry out the following:

(a) Issue (ii) on solving the interface issue will potentially increase the project cost. Examine the four options to cut/minimize project cots. Appraise the feasibility of each option in solving the problem. Propose the best option and evaluate the change in project cost.

(b) Incorporate issues (i) to (iii) and their solutions into the MS Project File. The project went on till completion. Set Status Date to two working day after the Finish Date of the Project (Activity 1). Then update the MS Project.

Construct a Tracking Gantt Chart. Determine the Finish Dates for "Test overall system" and for the entire Project.

(c) Evaluate and interpret the project's Cost Performance Index (CPI), by using appropriate formula Verify your CPI with a MS Project cost table or report.

Section 4: Closing a Project

Question 4

(a) Assess and discuss whether the project has met the objectives set by the CEO. Determine if the project is considered a success.

(b) Recommend two (2) actions that could have been done earlier to prevent the issues in Question 3 from occurring during the project or to minimise their impacts.

SECTION B -

The Senior Management of Digital Science Institute (DSI) asked you, Project Manager for 3D Printing Project, for a presentation one week after project completion. Your presentation should address the following issues:

1. What were the objectives and priorities of the project, and were they met?

2. Were there changes in the schedule and what were the contributing events?

3. Was there a cost overrun and what were the contributors for the cost overruns, if any?

4. Lessons learnt and suggestions for future projects.

Prepare a video recording of the presentation of at least 3 minutes but not exceeding 6 minutes. There are two methods for ECA video assignment submission; either Record Media or Upload Media For Upload Media,  please note that your file size should be no more than 500M B and the format is in .mp4.

SECTION C -

Prepare a set of PowerPoint presentation upon which the video presentation is based. Please note that the PowerPoi nt must be converted to PD F before submission to MyUniSIM (Canvas).

Attachment:- Assignment.rar

Reference no: EM131412025

Questions Cloud

Understand the important results and methods of given paper : The goals of the journal article critique are to understand the important results and methods of the paper and to evaluate the validity of the paper.
Draw a transistor-level schematic for four-bit manchester : Draw a transistor-level schematic for a four-bit Manchester carry chain. Use it to show the critical delay path for these values of a and b addends (assume that the carry in is 0)
What genre would your film fit in : What do you believe the ultimate argument of the novel Frankenstein to be? How can we develop this argument as part of a class in serial killer media? As this is the only novel that we'll be reading from the 18th century, how does this older work ..
Construct a narrative essay of around 800 words : Choose one and construct a narrative essay of around 800 words in the model of The New York Times "Lives" essays from the document attached.
Prepare and construct a gantt chart using the information : BUS353e Project Management. Prepare and construct a Gantt Chart using the information and steps outlined above before resolving any resource conflicts. Present the MS Project Gantt Chart View with columns for Information (i), Task Name, Duration, ..
Draw a schematic for a full adder cell : Size the transistors in a four-bit full adder using logical effort.
Personally think is biggest obstacle to making good decision : What processes do you go through to make good decisions? What do you personally think is the biggest obstacle to making good decisions? Do you think it is easier to make decisions as an individual or as part of a group?
Why does frankensteins monster kill in the novel : Why does Frankenstein's monster kill in the novel? This is a deceptively simple question, so let me elaborate just a bit. What is his reason and motive for revenge? How does the monster admit that all of his killing could have been avoided? What m..
Design a barrel shifter built from static gates : Design a barrel shifter built from static gates and clocked inverters. Draw a schematic for a cell and for a tiling of cells similar to the drawings for the pass-transistor version of Figure 6-3.

Reviews

len1412025

3/3/2017 2:16:36 AM

The THREE (3) items of Report, Video and Presentation Summary are to be submitted by 12 noon on the submission deadline. You are allowed multiple submissions till the cut-off date for each of the THREE (3) items. Late submission of any of the THREE (3) items will be subjected to mark-deduction scheme by the University. Please refer to Section 5.2 Para 2.4 of the Student Handbook. The Report: submit online to Canvas via Turnitln (for plagiarism detection) The Video: submit online to Canvas (refer to workshop invite for the user guide). The Presentation Summary: submit online to Canvas via Turnitln (PPT must be converted to PDF and submission is in PDF only) The PPT must contain at least 20 words. Refer to workshop invite for the user guide.

len1412025

3/3/2017 2:16:25 AM

Business Assignment. You have to do report and PPT. You don’t need to create the video. You are to include the following particulars in your submission: Title, Your PI, Your Name, and Submission Date. Late submission will be subjected to mark-deduction scheme by the University. You are required to submit the following THREE (3) items for marking and grading:- A Report (you should submit this item first as it carries the highest weightage). A Video Presentation: UniSIM conducts Hands-on workshop on how to record ECA video presentation for SBIZ students every semester. Students will receive an invite to the workshop via Student Portal, Canvas as well as email, a month before the ECA cut-off date. The ECA video recording and submission guides are also available as an external links/downloads in the invite. The set of PowerPoint slides, converted to PDF, upon which the video presentation is based. Please verify your submissions after you have submitted the above THREE (3) items.

Write a Review

Project Management Questions & Answers

  Effectiveness of training and minimize development costs

A partnership might be developed to maximize the effectiveness of the training and minimize development costs. Different delivery methods should be explored, including instructor-led, CD/ROM, and Web-based training. About half of employees would p..

  Find the critical path in your aon diagram

INFT6304 - Project Planning & Management Group Assignment. Find the critical path in your AoN diagram and the total duration of the project

  Investigate building your own home network

If you were to get a high-speed Internet connection like DSL or cable modem, how much would it cost? Can you buy your own, or would you have to rent the modem from the phone or cable company?

  Discuss the technical and other project management issues

Identify and discuss the technical, ethical, legal, contractual, and other project management issues that he has faced.

  Key stakeholders is important for effective communication

Just as deciding how to communicate with your key stakeholders is important, listening to your key stakeholders is important for effective communication.

  What is the option of using agile project management

What do you think about the option of using agile project management? Hunsberger (2011) sees change as something that should not be resisted or limited.

  Designing a quality power trim system

Design a quality power trim system. Design and build the equipment to produce such a system efficiently.

  Project management task trade show plantask project

project management task trade show plantask project management theory- deliverable length 3-5 pages- details your next

  Project manager and unforeseen risks - planning

Explain how should the project manager expand for the enterprise-level project and plan for these factors accordingly

  What did the court find wrong with the union spending funds

What did the Court find wrong with the union spending funds, which it had lawfully been awarded in arbitration proceedings, on political candidates supportive of union ideals and on charitable contributions for the good of the community.

  Work breakdown structure for the construction of building

Prepare a Work Breakdown Structure for the construction of the building. You should use all of the tasks the case has described as well as adding at least 10 of your own. It is NOT expected that the WBS be in MS Project, a Microsoft Word document ..

  Important information about project management planproject

important information about project management planproject management plananalyze the role of project management in

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd