In a single period order quantity model, if the underage cost is four times the overage cost, then

A) what is the optimal service level (i.e., critical fractile)?

B) using the optimal service level from part A), what is the optimal order quantity if the demand is normally distributed with a mean of 70 and variance of 9?

Reference no: EM13961271

Questions Cloud

Member roles specific demographic groups : Unions are especially popular in attracting to their member roles specific demographic groups and those with specific grievances. a) Describe the profile of individuals who are most likely to join a union and under what circumstances. b) What is the ..
Benefits of improving employee financial literacy : Staff members from the marketing department of your firm are doing a splendid job selling products to customers. Many of the customers are so pleased that they are also buying shares in the company’s stock, which means that they receive a copy of the..
Describe place where you work or worked in terms of grid : Without naming the company, describe a place where you work or worked in terms of this grid. Where does the company fall in the grid? Provide specific examples of decisions made by the company that demonstrate why it should be placed at a point on th..
Discuss how cds can be used for hedging : Discuss how CDS can be used for hedging and speculative purposes.
Order quantity model-what is optimal service level : In a single period order quantity model, if the underage cost is four times the overage cost, then what is the optimal service level?  using the optimal service level from part A), what is the optimal order quantity if the demand is normally distribu..
Find the optimal average backorder level : The Samuels Manufacturing Company sells a product with a demand of 7,000 units each year. The cost per order is $25, the holding cost is $1 per unit per year and the stock out/shortage/backorder cost is $4 per unit per year. What is the optimal quant..
What is the optimal production lot-size : Kellam Images prints snack food bags on long rolls of plastic film. The plant operates 250 days a year. The daily production rate is 6,000 bags and the daily demand is 3,500 bage sold at $2 each. What is the optimal production lot-size (economic prod..
A student put 1.18 mole of substance : A student put 1.18 mole of substance A and and 2.85 mole of substance B into a 10 litre flask which was then closed. The reaction that took place was: A(g)+ 2B(g) 3C(g) + D(g)
Due process clause issue : Jeff wants to open a French Fry Store called Jeff’s French Fries. Jeff lives in State X. State X Food regulating board says that if Jeff does not Fry the potatoes at 500 degrees Jeff will make his customers sick and must be shut down. Jeff thinks he ..

Reviews

Write a Review

Operation Management Questions & Answers

  Calculate the cycle time for the application process

The Central Evaluation Unit Task 1: Analyse and evaluate the processing of new applications at the CEUPU. Create a process map for new applications

  Develope mrp planning schedule

develope MRP planning schedule, specifying when items are to be ordered and received. There are currently no units of inventory on hand.

  Describe the different types of interviews

Describe the different types of interviews, and some problems encountered in interviewing.

  Discuss the role between internal worth and market value

Explain why more than one pay structure may be needed in an organization. Discuss the role between internal worth and market value.

  Proponent of decentralized form of socialism usually support

Proponents of decentralized forms of socialism usually support

  A description of how the elements directly associate to the

choose a specific organization preferably in an industry in which you are interested and use that organization as a

  What is the critical path

What is the critical path? Enumerate all the paths in the network. For the cost data shown below, reduce the project completion time by three weeks

  What are some of the challenges marketers must consider

What are some of the challenges marketers must consider when designing their pricing strategies?

  Discuss the proper preparation aspects of new product

Discuss the proper preparation aspects of new product development. Deduce why companies are feeling the pressure to bring new products to the market quickly.

  Production plans for chase and level strategies

The forecast for monthly demand is given below. On average there are 22 production days in a month. It takes one worker three days to complete one unit. The current production work force level is 50 employees. Develop separate production plans for ch..

  Prepare a comprehensive emergency management plan

Prepare a comprehensive emergency management plan based on actions to mitigate security threats. Identify preventative and mitigating actions that will reduce loss.

  What is the utilization rate of this service system

If "Fast Eddie" observes that the on call crews are idle about 50% of the time is he safe in assuming that they are not doing their job? Why do you so state?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd