Forecast for each week of an eight-week schedule

Assignment Help Operation Management
Reference no: EM131115677

Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) are follows: Week Customer Order 1 52 2 35 3 20 4 12 Use a production lot size of 73 units and no beginning inventory. (Leave no cells blank - be certain to enter "0" wherever required.) June July 1 2 3 4 5 6 7 8 Forecast 50 50 50 50 50 50 50 50 Customer Orders 52 35 20 12 0 0 0 0 Projected on-hand inventory MPS ATP

Reference no: EM131115677

Questions Cloud

Prepare the general journal entries to record the purchase : Prepare the general journal entries to record the purchase by A Ltd under AASB 3 Business Combinations and the payment to B Ltd. Narrations is not required.
Frequency distribution with class intervals : Construct a frequency distribution with class intervals of 3, starting with the lowest class limit being 28.
What width gives you the maximum area : What width gives you the maximum area - What is the maxmimum area? Round to the nearest tenth as necessary.
Describe the changes that a stage iii organization : Describe the changes that a Stage III organization must make in order to transition to the consolidation stage of Stage IV.
Forecast for each week of an eight-week schedule : Prepare a master schedule given this information: The forecast for each week of an eight-week schedule is 50 units. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Customer orders (committed) ar..
Prepare master production schedule for industrial pumps : Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to "schedule production when the projected on-hand inventory would be less than 10 without production." Suppose that a production lot siz..
Inventory beginning ending average backlog costs : Wormwood, Ltd., produces a variety of furniture products. The planning committee wants to prepare an aggregate plan for the next six months using the following information: Period 1 2 3 4 5 6 Total Forecast 160 150 160 180 170 140 960 Output Regular ..
Write an inequality that models the condition : Write an inequality that models the condition. Solve the inequality to find out how many calls must be made to make plan A the better choice
What would calculation and breakdown of calculation be : Blue Corporation's standards call for 3,900 direct labor-hours to produce 1,300 units of product. What would calculation and breakdown of calculation be

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd