Finding critical path and project duration

Assignment Help Project Management
Reference no: EM1337452

Given the following project to landscape a new building site.

Activity Immediate Predecessor Activity duration(days) Resources used

A: Get Plants - 2 X,Y
B: Get flowers A 2 X
C: Obtain soil A 3 X
D: Obtain Fertilizer B,C 4 X,Y
E: Select Labor D 3 W,X
F: Set date D 1 W,X,Y
G: BEGIN E,F 2 X,Y

(a) Find the critical path and project duration in days.

(b) Given that each resource is assigned 100% to each task, identify the resource constraints.

(c) Level the resources and determine the new project duration and critical path

(d) Identify what alternative solutions can be used to shorten the project duration and not over-allocate the resources.

Reference no: EM1337452

Questions Cloud

How will you access the size attribute of building : Write down a declaration for all three classes using the principles of inheritence. Make the Building class abstract.
Depends on the ideas two economists : Depends on the ideas, explain with which of the two economists do you agree more and explain why.
Determine the consequences of the risks : Determine the consequences of the risks are the potential consequences worth the risks?
Express currently used tools and recommended measures : Web phishing, pharming and vishing are popular web based scams. examine currently used tools and recommended measures to defeat this kind of attacks efficiently? Specifically focus on solutions that can be implemented at the network infrastructure ..
Finding critical path and project duration : Find the critical path and project duration in days. Given that each resource is assigned 100% to each task, identify the resource constraints.
Issue and effects of identity theft : Do you understand the issue and the effects of identity theft? Do you support the adoption of this legislation? Why or Why not?
Explain of how they may be used in an organization : Identification of features to be used as-is, possible modifications and additions.explain of how they may be used in an organization.
Explain why is it that a firm in a perfectly competitive : Explain why is it that a firm in a perfectly competitive market can sell as much as it wants without a change in price occurring? As a result, what is the elasticity of demand affecting the firm then.
Clarification of ratio analysis : Average Weighted Cost of Capital, Risk Premium, debt to equity and the Current assets of GPC Genuine Parts Company for the most recent 5 years.

Reviews

Write a Review

Project Management Questions & Answers

  Prepare a monthly profit report

Prepare a "Monthly Profit Report", Create this report using the results of your ABC overhead allocation.

  Completion time for project if duration of activity is given

What is the revised completion time for the project if duration of activity E is 3 weeks?

  Identify the technical challenges by project leader

Recommend three actions that the project leader should take in order to identify and understand the technical challenges and issues facing the project

  Protection to intellectual property

Compare and contrast the protection to intellectual property provided by trade secrets relative to that provided by patents.

  Determining sales contracts

Provide a well written answer of not less than 200 words to the following. Weaver Mills Co. in Country F contracted to purchase 100,000 yards of jute from Natural Fiber Co. in Country G at US$ 0.64 per yard. Natural delivered 22,228 yards

  Computing the portfolio risk

The covariance between the two stocks is -0.35. Find the portfolio risk if: the stocks are weighted equally in the portfolio.

  Project management and organization-s strategic plan

Describe the connection between Project Management and an organization's Strategic Plan.

  Important information to create a project organization chart

What information is most and least useful to a project leader when creating a project organization chart?

  Describing how to estimate effort

Describe how to estimate effort. Discuss why it is so important to estimate projects correctly.

  Explain most important aspect of project management

Explain most important aspect of project management.

  Forecast the cash flows generated by project

First, Forecast the cash flows generated by project X over its economic life. Second, determine the appropriate opportunity cost of capital(r).

  Explaining process to close a project

Explain the process you would use to close a project.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd