Find the optimal transportation cost

Assignment Help Other Engineering
Reference no: EM131449481

Decision Analysis & Modeling -

Question 1. Differentiate between "Pure strategy and Mixed strategy" in Game theory. Compare the two strategies using suitable examples.

Questio 2. Solve the following Transportation Problem (using Vogel's Approximation method) and find the optimal transportation Cost (using Stepping Stone Method)

Plants /
Warehouses

                       W1       W2      W3     Supply

P1                    33          26         24       550

P2                    21          28         31       350

P3                    25          24        29       600

Demand       400       600    500

Question 3. a. A project involves the following activities with the given durations and precedence requirements

Activity

Duration(weeks)

Precedence requirements

A

1

-

B

7

-

C

4

A

D

3

A

E

6

B

F

2

B

G

9

C,D,E

H

3

F

I

11

0,11

  I. Draw the network diagram of the project.

  II. Determine the critical path and duration of the project

  III. Which activities have slack and how much

b. Explain how the above project can be fast tracked.

Verified Expert

Reference no: EM131449481

Assignment on ttp1 for assign the experts

This plan must include each of the seven Integrated Team Projects and the TPP-2, including individual assignments, with leadership assigned to each assignment and working as

Write report based on finfet

Microelectronics Fabrication Homework- Write five pages report based on FinFET is the Beginning. Ideas, like what are challenges? What is after FinFET? How is going to change

What levels of the hierarchy of controls are most applicable

What levels of the hierarchy of controls are most applicable to system safety? Are any levels not useful when applying system safety? Provide one or more examples that suppo

The goals to achieve in the lab

Listthe type of equipment or components that you will be using? Where will you find these components? How will you use these components in Multisim/VHDL? Explain any adjust

Determine the minimum surge tank size

Assignment- Open Channel and Pipeline Flow: Determine the minimum surge tank size (nearest ½ m) to satisfy the max. allowable height. For the case of complete closure (Q chang

Evaporative crystallizer operating

An aqueous solution of potassium hydroxide is fed at a rate of 875 kg/h to an evaporative crystallizer operating at 10°C, producing crystals of KOH·2H2O. A 5 g aliquot of th

What is value of gm at which source follower is operating

The transfer function of the source follower is measured as RL is varied. At what value of RL will the transfer function be maximally flat? At this value of RL the dc gain i

Analyse a proposed redesign of dehavilland vampire tail

Your task will be to analyse a proposed redesign of the de Havilland Vampire tail booms (not to be confused with a boom in your hand calculations) in an all metal configurat

Reviews

Write a Review

 
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd