Explain what are the critical path activities

Assignment Help Operation Management
Reference no: EM13731732

Problem 1

The following data were obtained from an in-house MIS project-

Activity Duration Predecessors 

A        3 Days   ---          

B        6 Days   ---          

C        3 Days   B            

D        2 Days   A            

E        3 Days   C,D          

F        2 Days   A            

G        4 Days   F            

H        7 Days   B

I        2 Days   C,D

J        4 Days   H,I

K        8 Days   H,I

L        5 Days   E,G,Ja) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity E? Show your calculations.

f) What is the slack or float for Activity J? Show your calculations.

Problem 2.

A project to remodel an office area has the following activities.

Activity

Duration

Predecessors

A

3 months

---

B

2 months

---

C

3 months

---

D

4 months

A, B

E

3 months

A

F

2 months

B, C

G

2 months

F

H

1 month

G

I

4 months

D, E, F

J

5 months

H

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity B? Show your calculations.

d) What is the slack or float for Activity D? Show your calculations.

e) What is the slack or float for Activity F? Show your calculations.

f) What is the slack or float for Activity I? Show your calculations.

Problem 3

Information from a room addition project:

 

 

Duration

Predecessors

 

A

2 wks

 

 

B

3 wks

 

 

C

5 wks

 

 

D

7 wks

A

 

E

3 wks

B

 

F

2 wks

C

 

G

4 wks

F

 

H

1 wk

A

 

I

8 wks

D, E, G

 

J

5 wks

F

 

K

2 wks

D, E, G, H

 

 

 

 

 

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity A? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity H? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations.

Problem 4

InformAtion from a site renovation project:

Task     Duration            Predecessors

A          2 wks               _

B          5 WKS             A

C          3 WKS             B

D          15 WKS           B

E          8 WKS             C

F          10 WKS           C

G         2 WKS             D

H          6 WKS             E, F, G

I           5 WKS             H

a) What are the critical path activities?

b) What is the project's scheduled completion time?

c) What is the slack or float for Activity C? Show your calculations.

d) What is the slack or float for Activity F? Show your calculations.

e) What is the slack or float for Activity I? Show your calculations.

f) What is the slack or float for Activity K? Show your calculations.

Reference no: EM13731732

Questions Cloud

Is the following argument valid or invalid : Is the following argument valid or invalid? If valid, explain whether it is deductive or inductive. If invalid, explain why: "Mrs. Kelvin has accused me of intentionally denting her rear fender
What is the service level implied by ben''s reorder point : Suppose Ben decides to reorder 35 mm film when there are 86 rolls left in stock. How much safety stock is implied by this reorder point. What is the service level implied by Ben's reorder point of 86 rolls
Decision and discuss the effects : Explain which change model you would follow for the short-term change and which you would follow for the long-term change. Provide rationale for your decision and discuss the effects that these changes would have on the employees, managers, and ex..
How much each country consume each good : Think of a 2 country world, say the US and the UK. Each country produces two goods, say food and cloth. Suppose 7 hours of labour are required to produce one unit of either good in the UK, whereas in the US it takes 2 hours to produce one unit food a..
Explain what are the critical path activities : What are the critical path activities. What is the project's scheduled completion time. What is the slack or float for Activity C
About database design and methodology : We learned about database design and methodology. You are the database administrator for your company, which has just acquired a company called SNHU Appliances. You are deciding what the best approach is. Should you merge your database with the new c..
Specify the most significant advantages and disadvantages : Specify the most significant advantages and disadvantages that could be realized by the organization in adopting a server virtualization infrastructure. Prepare a plan for implementing Hyper-V (or an alternate solution, such as VMware) as a solution ..
General aggregate statistics: total number of tickets sold : Present the data in a professionally formatted worksheet such that it is easily viewed/understood. Since visualization aids in understanding data, include an appropriate chart to illustrate each set of data. Lastly, analyze the data and provide any c..
What strategies could you and new soft drink company use : According to Porter's discussion of industry analysis, is Pepsi Cola a substitute for Coca Cola? what strategies could you and your new soft drink company use to impact the dominance of Pepsi and Coke in the global marketplace? Why

Reviews

Write a Review

Operation Management Questions & Answers

  Explain how impleminting lean principles in an organization

explain how impleminting lean principles in an organization could help with overall riskmitigation for that organization.

  How small business give affordable health care to employees

How can a small business provide affordable health care to their employees? How does offering health insurance benefit small business beyond attracting good employees?

  Problem on inventory control

Carmin's Boutique sells a large number of black dress shirts. The shirts, which bear the store label, are shipped from a manufacturer in Paris. Carmin's purchasing department manager says, "I want to be sure that I never run out of dress shirts.

  What are three way to shorten the time required

what are three way to Shorten the time required to complete the work on the critical path may be done?

  Calculate 95 percent confidence interval for population mean

Health insurers and the federal govt are both putting pressure on the hospitals to shorten average length of stay of their patients.

  Discuss the key factors in the international environment

Discuss the key factors in the international environment that managers of emerging global organisations look to as threats to their international operations. Provide examples as appropriate.

  Develop a specific plan and appropriate budget

your paper will address a plan for the operations of a sole proprietorship business in a service of manufacturing industry. At a minimum, your paper should Identify relevant issues and develop a specific plan & appropriate budget

  Evaluate the challenges for profit public companies

Evaluate the challenges that for-profit public companies face from recurrent scandals, political attacks and alternative corporate structures such as the B-corp.

  Construct the linear programming model

A farmer has 10 acres to plant in wheat and barley. He has to plant at least 7 acres. However, he has only $1200 to spend and each acre of wheat costs $200 to plant and each acre of barley costs $100 to plant

  What is the geometric mean change in the cost

9. are there any outliers in the change in cost? 10. construct a boxplot of this sample ( lable axis and the five-number summary.)

  Do you concur with the dispute settlement decisions

Do you concur with the dispute settlement decisions in the World Trade Organization in this case? The panel report? The appellate decision? The arbitration ruling?

  American business alliance versus the ceo of rush trucking

Andra Rush belongs to several volunteer organizations. Would her leadership style need to change as the president of the Native American Business Alliance versus the CEO of Rush Trucking? How would the Community Leadership Model apply to Andra Rus..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd