Draw the activity-on-node project network

Assignment Help Operation Management
Reference no: EM131229898

Suppose a project consists of the following activities. Activity Immediate Predecessors Time (Days) A None 5 B None 8 C A 4 D B, C 6 E B, C 4 F D 6 G E, F 4 (a) Draw the activity-on-node (AON) project network based on the table above? Only nodes and directed arrows are required in the network for full credit. Add a dummy start node with 0 activity time. (b) List all the paths in the network and calculate the completion time of each path for full credit. (c) What is the project completion time? Please give the reason for full credit.

Reference no: EM131229898

About the information technology

As IT applications become more reutilized all across the board, one of the interesting features are the occasional employees who know more than the IT staff about some critica

When have others conflicts of interest impacted

When have others’ conflicts of interest impacted how you or those you know were treated? Why do you believe conflicts of interest are so pervasive in society? Why don’t we tak

Identify a journal article relevant to your industry

identify a journal article relevant to your industry (past, current, or intended) and describe why that article helps you understand a component of motivation within your in

Discuss the pros and cons of cumulative voting vice

Discuss the pros and cons of cumulative voting vice regular voting for Directors of a company. Why would a company choose one over the other? Who benefits from each type: sh

Capacity utilization rate-capacity focus and flexibility

Jill is concerned that the latest short term demand forecast for dog grooming at her fifteenth street dog salon is higher than her salon capacity. As she doesn't want to turn

There are seven mistakes when managing processes

There are seven mistakes when managing processes, arguing that failure to manage processes is ultimately a failure to manage the business. In 2-3 sentences for each mistake, d

What is your evaluation of the process of going closure

What is your evaluation of the process of going about the closure. Was RSPS demonstrating social responsibility. Discuss the closure impact on three specific stakeholders.

Assignment on tracking progress on sustainability goals

Assignment On Tracking Progress on Sustainability Goals. Good intentions must be followed by actions leading to measurable outcomes. Sustainability initiatives and their out

Reviews

Write a Review

 
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd