Draw an aon and time-based network diagram

Assignment Help Project Management
Reference no: EM13825017

12. A project manager at Kippy Jo's Cosmetics wishes to determine total human resource needs for an upcoming marketing campaign involving three of the company's products. Each product will be marketed through a different medium. Precedence relationships for project tasks, along with resource information, are highlighted in the table below:

Task                                                   Duration (Days)    Immediate Predecessor    Resource Requirement (# Staff Members Required per Day)

   A. Research, Product 1                         3                                         None                                                                                 4

   P. 2                                                           2                                         None                                                                                 5

   P.3                                                            3                                         None                                                                                 6

   P.4                                                            2                                             A                                                                                    6

   P.5                                                            9                                             A                                                                                    5

   P.6                                                            3                                             B                                                                                    5

   P.7                                                            3                                             B                                                                                    2

   P.8                                                            2                                             C                                                                                    4

   P.9                                                            0                                     D, E, F, G, H                                                                          0           

 

a. Draw an AON and time-based network diagram and identify the critical path in each one.

b. Calculate the daily resource loads for the project. (You may wish to use Excel although this problem is small enough to lend itself to a manual approach.)

c. Scenario 1, Time Constrained: Revise the schedule to smooth resource requirements without changing the project's duration. No task splitting or task com- pression (crashing) will be allowed. Write a few sentences about the managerial implications of this revised schedule.

d. Scenario 2, Resource Constrained: Return to the original early-start schedule and assume the number of staff members has been limited to 10. Reschedule the project to accommodate this constraint. As in Part C, you may not split or compress tasks. You will have to change the project's end date, so your goal will be to meet resource constraints with the shortest possible project duration. Write a few sentences about the managerial implications of this schedule.

Reference no: EM13825017

Questions Cloud

How much is the direct materials cost standard : Wood Designs Company, a custom cabinet manufacturing company, is setting standard costs for one of its products. The main material is cedar wood, sold by the square foot. How much is the direct materials cost standard (per square foot)?
Compute the current price of the bond : A $1,000 face value bond was issued at par 20 years ago with a 6% coupon paid semiannually. The bond now has nine years remaining to maturity and similar debt obligations are yielding 12%. Compute the current price of the bond. Assuming that the bo..
Transport principles of economy of scale and distance : transport principles of economy of scale and economy of distance
Start saving for retirement : You would like to start saving for retirement. Assuming you are now 25 years old and you want to retire at age 55, you have 30 years to watch your investment grow. You decide to invest in the stock market, which has earned about 12% per year over the..
Draw an aon and time-based network diagram : a. Draw an AON and time-based network diagram and identify the critical path in each one.b. Calculate the daily resource loads for the project. (You may wish to use Excel although this problem is small enough to lend itself to a manual approach.)
Which option is the lowest-cost alternative for star studios : Star Studios is looking to purchase a new building for its upcoming film productions. The company finds a suitable location that has a list price of $1,540,000. The seller gives Star Studios the following purchase Which option is the lowest-cost alte..
Major criticism of utilitarianism ethical theory : Under which ethical system would it be ethical to compel a few citizens to undergo painful or fatal medical tests in order to develop cures for the rest of the world?
Prepare journal entries for the following transactions : Prepare journal entries for the following transactions involving notes payable for Homer Company, whose fiscal year ends June 30. Omit explanations
Immanuel kant approach on ethical decision : If a Middle Eastern culture and an East Asian culture differ as to the morality of a particular action, under ethical relativism:

Reviews

Write a Review

Project Management Questions & Answers

  Evaluating potential projects before implementing it

Why do you think it is important to evaluate potential projects before proceeding with implementation?

  Identify the company''s internal and external stakeholders

Identify the company's internal and external stakeholders.

  The types of company projects that can make or break careers

IS are the types of company projects that can make or break careers in some cases. Get it right, and you can be looking at a bright future at a company. Get it wrong, and that future may become quite clouded.

  Business ethics-policy statement

Select Dell Inc. as your business and develop the environmental policy statement for that organization. The policy statement must have the following components below:

  Project management-conflicting agendas

How can you use the organization's culture to help minimize conflicting agendas that the team members may have to deal with - Project Management-Conflicting agendas

  Lowest ratio mixed assembly planningfor that mixture what

lowest ratio mixed assembly planningfor that mixture what is the lowest ratio mixed model assembly sequence?in

  Information systems questionswhat elements need to be

information systems questionswhat elements need to be considered in developing a cost estimation for a project?how does

  Explaining triple constraints

What are the triple constraints? What key elements are interrelated? What happens if one of the elements changes?

  History has shown that project team members often question

history has shown that project team members often question whether they can trust their project team leaders technical

  Steps of quality management process improvement

Outline the steps of your quality management process improvement and implementation plan.

  Describe by fully defining and illustrating brooks law

Describe by fully defining and illustrating Brook's Law. List the members of a 10-man programming team built on the surgical model and describe their tasks

  Expert response to project managementin my role as project

expert response to project managementin my role as project manager for my group called the the provision healthcare

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd