Assignment relates to scheduling in project management.
Question 1: Given the activity below. please draw an activity-on-arrow network on page 4.
Question 2: Given the sub networks below, follow all conventions used in class and calculate the four activity times for Activity B. No splitting allowed.
Question 3: Given the sub networks below, follow all conventions used in class and calculate the four activity times for Activity B. No splitting allowed.
Question 4: Calculate the schedule on the next page for the case of no splitting. Complete the forward pass and start the backward pass and place your answers in the table.
Question 5: Calculate the schedule on the next page for the case of no splitting. Complete the forward pass and start the backward pass and place your answers in the table.
Activity ID
Early Start
Early Finish
Late Start
Late Finish
Float
A
1
10
B
14
21
C
11
30
D
E
19
F
43
G
45
46
H
47
52
I
37
39
J
Prepare a CMS/PM Projects on Green Footprint Ecotourism. This client is an eco-tour operator in Sydney that operates in the Blue Mountains, Royal National Park and Jervis Bay.
1. justify the use of tools and techniques used in project management including gantt charts and project network
What is the critical path of this project now? (i.e., list the tasks on the critical path of this project in order.) Suppose task G runs late. Change its duration to 8 in MS Project. Save the changed file with a file name of " H4.mpp".
project management as a careeri need an essay on project management. the only requirements for the essay aremiddotan
Describe why the project sponsor is one of the most important stakeholders, and what a project manager should do to keep them informed of the status of a project. Provide professional examples if possible.
Non-verbal communication during an interview - explain what are some examples of non-verbal communication?
Choose a project leader who has influenced you the most in your life or career.
Will you briefly describe this principle and what it is about - which one is the most important and why and how does this communication principle help one understand organizational communication
Evaluate Minimum cost of project crashing - What is the minimum cost of crashing the following project by 4 days?
Provide your thoughts on what the purpose of a problem solving meeting is and how would one be conducted?
Create a mission and vision statement for your organization and determine at least three specific strategic goals that align with the ideals in those two statements.
How to Respond to Risks - As a project manager, the risk assessment is one of the most important pieces of project documentation.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd