1. Which of the following is a tool to visually display the interrelationships between activities in a project? Check all that apply.
A bill of material diagram.
An activity-on-arrow diagram.
A tree diagram.
An activity-on-node diagram.
A work breakdown structure diagram.
2. An inventory management system based on a requirements philosophy creates orders from?
a. master production schedule
b. customer requests
c. sales and operations plan (S&OP)
d. Forecasts
3. The job of the project manager is to
a. keep within the budget, no matter what.
b. control costs, schedule, and performance of the project.
c. all of these choices.
d. control all costs.
4. Project control is best maintained by
a. the top managers who authorized the project.
b. the project manager.
c. a team member specifically assigned to control the project.
d. the cross-functional team.