Reference no: EM131129952
With the company expanding into several new markets in the coming months, Cable & Moore was anticipating a large increase in sales revenue. The future looked bright for this provider of television, telephone, and Internet services. However, management of Cable & Moore was well aware of the importance of customer service in new markets. If the public had problems with new service and could not quickly and efficiently have their problems solved, demand would quickly erode and it might take years to recover from the bad publicity. Therefore, management was adamant that there would be enough well-trained customer service representatives to handle the calls from new customers and from potential customers.
Based on experience in other markets, the anticipated number of phone calls to customer service was projected. Given the average call-length, the number of hours of customer-service time from April to August was projected and is shown below.
Month April May June July August
Hours needed 22,600 24,600 27,200 28,100 29,500
Through experience, management knew that training a new employee well was essential. Each new employee was put through a 1-month training program, and was assigned to an existing employee for an entire month. Normally an existing employee would work 160 hours per month. However, when an employee was assigned to perform training of a new-hire, the productive work hours for that employee dropped to 80 hours per month.
During the training period, the trainee was paid $2,000 for the month. At the end of that time, the monthly salary increases to the standard salary for a regular customer service representative which is $3,500 per month. In the past, the company lost about 5% of the trained customer service representatives per month due to attrition. While the company is looking to improve upon this, for the next several months it is anticipated that this will continue. There will be 170 trained employees at the beginning of April. Management of the company would like to develop a schedule of hiring new employees so that there are sufficient customer service representatives to meet the demand, but this is to be done at the lowest possible cost.
Discussion Questions
Develop a schedule for hiring new employees. What is the total cost of this schedule?
Discuss any limitations that exist for this solution.
How would the schedule change if the attrition rate could be lowered to 3% per month instead of 5%? What would be the impact on the cost?
Based on the science of robotics and artificial intelligence
: Describe the form (the physical thing created, or, for a service, the set of steps by which the service will be created) of the product you selected. For example, science behind automated vacuum cleaners (product) uses technology that is based on the..
|
What is your definition of democracy
: What is your definition of democracy? On the whole, has technological advance increased or decreased the amount of democratic participation in modern society?
|
Find the slight error in givne code
: This is my code and it has a slight error, can someone fix this code for me. I need it to compile. Please fix whatever error is within this code
|
Describe the product and process innovations associated
: If product innovation is defined as the manner by which the attributes of a product (a good not a service in this case) provide customer benefits and process innovation is defined as the methods by which important product attributes are incorporated ..
|
Develop schedule for hiring new employees
: With the company expanding into several new markets in the coming months, Cable & Moore was anticipating a large increase in sales revenue. The future looked bright for this provider of television, telephone, and Internet services. Develop a schedule..
|
What the effect of the cultural and social risks
: what the effect of the cultural and social risks that will pose a threat on the well-being of the organization, using the cultural and social characteristics of the region
|
What is the probability that all machines are working
: An operator is in charge of FIVE machines. After each machine completes a job, the operator must reset it before a new job is started. In other words, the operator’s task is to set up each machine when a job is completed. Determine the average number..
|
How much the insurer will pay for each victim
: Assume that the insured carried 100/300/50. Imagine the following claims filed by injured parties in the other vehicle: ? X sustains $90,000 in bodily injuries, Y sustains $120,000 in bodily injuries, and Z sustains $100,000 in bodily injuries, W sus..
|
What is comprehensive or integrated-rural development
: Briefly state the economic and noneconomic arguments in favour of land reform in Latin America and the Caribbean. What is comprehensive, or integrated, rural development? What are the main arguments of the trade optimists? Is this position supported ..
|