Determine the total project completion time

Assignment Help Operation Management
Reference no: EM13833710

McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:

 

  • Activity 1: Measure office room dimensions
  • Activity 2: Estimate cost
  • Activity 3: Material requisition
  • Activity 4: Workforce requisition
  • Activity 5: Special tool requisition
  • Activity 6: Installation
  • Activity 7: Inspection and customer acceptance

 

Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:

 

Activities

OT

MT

PT

Activity 1

4

6

14

Activity 2

5

12

16

Activity 3

7

15

23

Activity 4

13

16

28

Activity 5

17

20

35

Activity 6

20

32

50

Activity 7

5

6

13

 

You must also do the following:

 

  • Determine the expected completion time and the variance for each activity
  • Determine the total project completion time and the critical path for the project
  • Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
  • What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
  • Define project management and the necessary requirements.
  • Analyze implications of changes in project scheduling.
  • Evaluate application of project management techniques in terms of the firm's business operational goals and requirements.

Reference no: EM13833710

Understanding of business-to-business activities

In order to have a better understanding of business-to-business activities (“B2B”), locate an example of an existing business on the Web that is similar to your e-business. De

These are pretty important documents

After all, these are pretty important documents! After you have read the above documents, please consider what our Founding Fathers were thinking when they wrote and acted on

Statements about leadership

Which of the following adjectives is increasingly associated with today's top leaders? Many well- known individuals in the computer technology industry have become great leade

Concept of long tail relationship to netflix business model

Discuss the company's business strategy and how it has evolved. What firms are Netflix's most significant competitors, and how the nature of competition has changed in the ind

What is the optimal replenishment policy for the supplier

A retailer sells 5000 units of a product per month at a steady rate. The product is bought from the supplier at a wholesale price of $2.50 per unit. Without cooperation, what

What is the current state of the russian economy

Write a one page memo. Moscow is teaming with new construction sites high-end cars and new restaurants. I am the CEO of a growing international restaurant chain. What is the '

Various methods of intellectual property protection

How broad can a covenant not-to-compete be drafted and still be enforceable to protect the employer? Discuss the various methods of intellectual property protection available

Include technology-social factors-competition and regulation

What are some recommendations that include specific details on how to improve the overall functionality and utility of a hospital for a current PHR system in place. Include Te

Reviews

Write a Review

 
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd