Consider the following table and answer the questions that follow
Activity
Description
Predecessor
Optimistic time in days
Most likely time In days
Pessimistic time in days
A
Position recruiting
5
8
17
System development
3
12
15
C
System training
4
7
10
D
Equipment training
23
Manual system test
B,C
1
F
Preliminary system change over
13
G
Computer personnel Interface
0,E
6
9
H
Equipment modification
D,E
2.5
Equipment testing
System debugging
and Installation
F,G
2
Equipment changeover
1,1
11
1.1 Determine the expected activity times
1.2 Develop an activity on arrow network diagram (ADA)
1.3 Determine the earliest start and finish times; and the latest start and finish time
1.4 Determine the critical path
1.5 Determine the expected project duration
communication managing project communicationsexplain the tools a project manager may use to control and manage project
important information about project proposalprepare a project proposal how to lead and meet the needs of the customer
brian sanders had recently been appointed to the ceo position of the acme fireworks company. brian came from outside
project managementdo you think by informing the customer that you need more time for a project or the quality of the
project management changes to baselineunder what conditions would a project manager make changes to a baseline and be
Define the time frame for recruitment and orientation training.
The layout needed to manufacture the computer
Explain communication in Groups - Show analysis on how communication in groups differs from individual communication
Write a paper about importance of project Manangement and how it impacts your daily life.
a manufacturer has identified the following options for obtaining a machined part: It can buy the part at $200 per unit (including materials); it can make the part on a numerically controlled machine at 65$ per unit
Explain the similarities and differences between an adaptive project management life cycle model and an extreme project management life cycle model.
project managementbehavioral aspects of project management paperconsider the following scenario you have just been
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd