Describes critical path and pure project

Assignment Help Operation Management
Reference no: EM131229817

1. Which of the following describes a critical path?

a. The path taking longest time through this network of activities

b. The path taking shortest time through this network of activities

c. Hierarchy of project tasks, subtasks, and work packages

d. Stable workforce, variable work hours

2. Which of the following describes a pure project?

a. Inventory on hand and financing costs for that inventory

b. A self-contained team works full time on the project

c. Project houses within a functional division

d. Blend of pure and functional project structures

3. Which of the following describes the benefit of a functional project?

a. The project manager has full authority over the project

b. Team pride, motivation, and commitment are high

c. Technical expertise is maintained within the functional area

d. Needs of the client are secondary and are responded to slowly

Reference no: EM131229817

Questions Cloud

Minimum number of female applicants the company should hire : Central Valdosta Manufacturing Corporation had 100 male applicants last year. They hired 60 of them. They also had 50 female applicants of which they hired 20. In order to avoid adverse impact, what is the minimum number of female applicants the comp..
Consider the two auto manufacturing plants : Consider the two auto manufacturing plants below: How much is the annual output of each plant? How much is the flow time in each plant? How much is the WIP inventory in each plant?
How should project risks be monitored and controlled : How should the risks be prioritized? Who should do the prioritization of the project risks? How should project risks be monitored and controlled? Who should develop risk responses and contingency plans? Who should own these responses and plans?
What should be considered when identifying risks : Assume you have just been assigned to a project risk team composed of five members. Your task, as project manager, is to develop a process for handling risks to the project. What methods should be used for identifying risks? Who should be involved in..
Describes critical path and pure project : Which of the following describes a critical path? Which of the following describes a pure project? Which of the following describes the benefit of a functional project?
Independent hotel-caters to both business-leisure travelers : The Evanstonian is an upscale independent hotel that caters to both business and leisure travelers. On average, one-third of the guests checking in each day are liesure travelers. Leisure travelers generally stay for 3.6 nights-twice a long as the av..
Ethics-business organizations : In hiring a prospective employee, there are legitimate reasons for not hiring someone. For example, the prospective employee may not meet legal requirements. Identify and clearly define the relevant law utilized by the court in determining the outcom..
About diversity in a multicultural environment : Write a paper with at least 300 words about Diversity in a Multicultural Environment. Make a summary and give a reference or two to how you personally can use and implement this information in your life. This is a reflection paper.
Why should skipper products implement a ppm : You are the CEO for Skipper Products. The business has had a great year and you see that a PPM is needed to manage all the projects that are currently in progress, along with future projects. Why should Skipper Products implement a PPM?

Reviews

Write a Review

Operation Management Questions & Answers

  How a marketing professional assures the research

Include in your discussion the reasons why accurate marketing information is important to a company and how a marketing professional assures the research or information is correct.

  Directors of windsor memorial hospital has hired you to be

directors of windsor memorial hospital has hired you to be their zero-based budget consultant. specify how windsor

  Think of the use of cost-benefit analysis

What do you think of the use of cost-benefit analysis for determining whether some social policy ought to be supported? In particular, do you think that in comparing costs and benefits, we can legitimately place a monetary value on so-called “intangi..

  Bcg matrix to analyze kraft''s strategic plan

Apply SWOT, Porter's Five Forces, or the BCG Matrix to analyze Kraft's strategic plan to expand into international markets. How would you determine which markets to target short versus long term

  Describe a decision-making scenario

Describe a decision-making scenario using your business experience, personal decision making or cited journal article; include an example of the decision-making process, describe the risk, and whether persuasion was used. What were the social heur..

  How can rest of the nation help the unfortunate ones cope

How can the rest of the nation help the unfortunate ones cope with the impact of international trade?

  Moral obligation to give passante the stock

If you were on the jury, how would you decide the case? Was the offer of 3% of the firm's stock legal consideration for the loan or was it a mere gift? Does Upper deck have a moral obligation to give Passante the stock? If so, is this legally enforce..

  Units of a major product and found the processing time

You’ve just completed a pilot run of 10 units of a major product and found the processing time for each unit was as follows: Use Exhibit 6.4 and Exhibit 6.5. According to the pilot run, what would you estimate the learning rate to be? Based on(a), ho..

  About maldistribution of health care service personnel

What do we mean when we talk about "maldistribution" of health care service personnel? How does this impact policy efforts at improving quality and access and lowering health care costs? What policies would you recommend to address the different type..

  What do you think are the operational strengths of UPS

What do you think are the operational strengths of UPS? How have they achieved these strengths? How do their strengths match their marketing messages, some of which can be seen below?

  Social media instead of traditional forms of communications

Some research suggests that the younger generations spend too much time using Social Media instead of traditional forms of communications and that has hampered their ability to communicate effectively using traditional communications methods in the w..

  Different categories of air cargo systems

Write a two to three page report summarizing the different categories of air cargo systems. Include information on the following: Description of each air cargo system, Advantages of each system, Disadvantage of each system.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd