Define the work breakdown structure

Assignment Help Operation Management
Reference no: EM13729850

Put components for Part 1 of assignment here:

Develop an in-depth schedule for your initial project based on the Work Breakdown Structure you have completed in Unit III. Please refer to the "INTEGRATED PROJECT: Developing the Project Schedule" Be sure to include-

1. An activity precedence diagram

2. An activity duration table

3. A network diagram and Gannt charts

Exercise 1

Suppose we have a complete activity predecessor table (shown below) and we wish to create a network diagram highlighting the activity sequence for this project. Using MS Project, enter the activities, their durations, and their predecessors for activities A through E. Note that all duration times are in days.

Project: Remodeling an Appliance

Activity

 

Duration

Predecessors

A

Conduct competitive analysis

3

 

B

Review field sales reports

2

 

C

Conduct tech capabilities assessment

5

 

D

Develop focus group data

2

A, B, C

E

Conduct telephone surveys

3

D

F

Identify relevant specification improvements

3

E

G

Interface with marketing staff

1

F

li

Develop engineering specifications

5

G

I

Check and debug designs

4

Ii

1

Develop testing protocol

3

G

K

Identify critical performance levels

2

1

L

Assess and modify product components

6

I, K

M

Conduct capabilities assessment

12

L

N

Identify selection criteria

3

M

0

Develop RFQ

4

M

P

Develop production master schedule

S

N, 0

Q

Liaise with sales staff

1

P

R

Prepare product launch

3

Q

Exercise 2

Now, continue developing your Gantt chart with the rest of the information contained in the table above and create a complete activity network diagram for this project.

Exercise 3

Identify the critical path for the project shown in Exercise 1. How can you tell? Hint Click on the "Tracking Gantt" option.

Exercise 4

Suppose that we wished to incorporate lag relationships into a Remodeling an Appliance activity network. Consider the table shown below and the lag relationships noted. Develop an MS Project Gantt chart that demonstrates these lags.

Activity                          Duration               Lag Relationship

A Wiring                             6                             None

B Plumbing                          2                             None

C HVAC                              3            Wiring (Finish to Start), Plumbing (Finish to Finish)

D Interior  Construction         6                     HVAC (Start to Start)

Reference no: EM13729850

Questions Cloud

Unethical behavior of job applicants affect an organization : How does the unethical behavior of job applicants affect an organization? Describe the consequences of unethical job applicants for each member of the Triad.
How technology contributes to health care system in u.s. : Brief discussion regarding how each technology contributes to health care system in the U.S - Assess how each medical technology types affects or affected clinicians and organizations
Determine criteria for defining modern popular culture : Determine criteria for defining modern popular culture
What criticisms or challenges did they face from opponents : What criticisms or challenges did they face from opponents? Now does the person connect to the theme(s) presented in that week's lectures? Why are these individuals significant?
Define the work breakdown structure : Develop an in-depth schedule for your initial project based on the Work Breakdown Structure you have completed in Unit III. Please refer to the "INTEGRATED PROJECT: Developing the Project Schedule" Be sure to include: An activity precedence diagra..
Effective at reforming juveniles : Is the juvenile justice system effective at reforming juveniles? How many juveniles that go though the juvenile justice system reformed?
Sustainable competitive advantage is the holy grail : Using all you have learned to date about Harley-Davidson, analyze whether or not Harley-Davidson has a source of sustainable competitive advantage. Defend your answer using examples from your readings, the annual report, and other sources.
Understanding of virtual team management : The project will test your understanding of virtual team management using documents and events that will make the project team more productive.
Barker inc. uses the weighted-average method : Barker Inc. uses the weighted-average method in its process costing system. The following data concern the operations of the company''s first processing department for a recent month.  Work in process, beginning: Units in process 1000 Stage of compl..

Reviews

Write a Review

Operation Management Questions & Answers

  Create a design for a software interface

Your goal is to create a design for a software interface. You will experience the scope of the design process from brainstorming ideas and gathering information about users' needs to storyboarding, prototyping, and finally, testing and refinin..

  Calculate the labor productivity of the line

Riverside Metal Works produces cast bronze valves on a five-person assembly line. On a recent day, 180 valves were produced during an 8-hour shift. Calculate the labor productivity of the line.

  Discuss the impact entrepreneurs have on the economy

Discuss the impact entrepreneurs have on the economy. Highlight at least one benefit and one potential downside.

  What are some of the basic requirements for the project plan

What are some of the basic requirements for the project plan in order for EVM to be able to work?

  Brands can play a number of specific roles in a companys

brands can play a number of specific roles within a companys brand portfolio. for example a is positioned with respect

  Question 1 1you currently make a part on old equipment at a

question 1 1.you currently make a part on old equipment at a cost of 50000 per year and a variable cost of 20 unit.

  Estimate the break even point

A manager must decide how many machines of a certain type to purchase. Each machine can process 100 customers per day. One machine will result in a fixed cost of $2000 per day.

  Illustrate what is the break-even point

Illustrate what is the break-even point. Explain how many units must be sold to make a profit of $6000.00. Explain how many units must be sold to average $25 profit per unit? $50 profit per unit? $150 profit per unit.

  Explain how might aggregate production planning benefits

Explain how might Aggregate Production Planning (APP) benefit Wilkins. Illustrate what are the risks of using APP at Wilkins. Illustrate what constraints are most critical in the development of the aggregate plan at Wilkins.

  Does the company have a social responsibility to customers

In their marketing campaigns does the company have a social responsibility to these customers?

  Compute a three week moving average forecast

The numbers of patient arrivals to the ER department at a local hospital for the past 5 weeks are: week: 1 , 2 , 3 , 4 , 5 arrivals: 405 ,420 , 400 , 380 , 411

  In your opinion should the company provide consideration to

1. what was lee apparel companys overall goal for conducting such an extensive test market of its new line of jeans

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd