Reference no: EM13988190
Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise.
Time to Complete Task (seconds):
Task 1: 30
Task 2: 25
Task 3: 15
Task 4: 20
Task 5: 15
Task 6: 20
Task 7: 50
Task 8: 15
Task 9: 20
Task 10: 25
Task 11: 15
Task 12: 20
The current conveyor-paced assembly-line configuration assigns the workers in the following way:
• Worker 1: Tasks 1, 2, 3
• Worker 2: Tasks 4, 5, 6
• Worker 3: Tasks 7, 8, 9
• Worker 4: Tasks 10, 11, 12
Assume a demand rate of 20 units per minute. What would be the target manpower?
Strategic global marketing plan
: Your work on your strategic global marketing plan is complete. You now have a plan that will implement, manage, and support a global strategy, but it is far from organized. You e-mail Deborah to inform her that you are almost ready and that the pr..
|
Strategy allows firm to practice form of concentrated growth
: For success in mature industries, business strategies require which of these features? Strategy allows a firm to practice a form of concentrated growth by identifying new uses of existing products and by finding new demographic or psychographic marke..
|
What velocity does it reach in this time starting form rest
: A dish with a mass of 0.4 Kg has a force of Kinetic friction of 0.15 N exerted on it by a moving tablecloth for a time of 0.2 sec- What velocity does it reach in this time, starting form rest and how far (in cm) does the dish move in this time?
|
Could you live with the secret you know
: what if you didn't say anything and you gained that promotion. Could you live with the secret you know and how many other lives you might have ruined?
|
Conveyor-paced assembly line-machine-paced line flow
: Consider the following tasks that must be assigned to four workers on a conveyor-paced assembly line (i.e., a machine-paced line flow). Each worker must perform at least one task. There exists unlimited demand unless stated otherwise. Assume a demand..
|
What is the angular acceleration of the disk
: A disk 15 cm in diameter rotates counterclockwise in a horizontal plane, accelerating uniformaly from 33 rpm to 45 rpm in 1 min. What is the angular acceleration of the disk?
|
Compute the total cost of the entire inventory
: A local Chevrolet dealership carries the following types of vehicles: Because of recent Increases in gasoline prices, the car dealership has noticed a reduced demand for its SUVs, vans, and trucks. Compute the total cost of the entire inventory.
|
Company that buys and rents real estate
: Parsa Real Estate is a company that buys and rents real estate. The company is looking into buying an office building for $1M. The building has 10,000 square feet of rentable office space. The building needs to be maintained (security, insurance, mai..
|
Find the force p
: The disk and hub together have a mass of m=5 kg and mass moment of inertia (about the center) I=2 kgm^2. The disk radius is 3 m and the hub radius is 1 m. The disk rolls without slip. If after 1 revolution, the angular velocity of the disk and hub..
|