Compute the cost per broadcast hour during august

Assignment Help Managerial Accounting
Reference no: EM131318135

Question:

WMTB is an independent television station run by a major state university. The station's broadcast hours vary during the year depending on whether the university is in session. The station's production crew and supervisory costs are as follows for August and October.

Cost Item Cost 
Behavior Cost 
Amount Broadcast Hours 
during Month 
Production Crew Variable
August $ 5,940 450
October 8,712 660
Supervisory employees Fixed
August 5,900 450
October 5,900 660

Required:

1. Compute the cost per broadcast hour during August and October for each of these cost items. (Round your answers to 2 decimal places.)

2. What will be the total amount incurred for each of these costs during December, when the station's activity will be 480 broadcast hours?

3. What will be the cost per broadcast hour in December for each of the cost items? (Round your answers to 2 decimal places.)

Reference no: EM131318135

Questions Cloud

Develop the disaster management program : BACS2063 Data Structures and Algorithms Assignment. Application that uses the ADTs -Develop the disaster management program (console/GUI), which at least includes the following functionalities: Maintain food and supply, such as add new food/supply, u..
Which is not considered a type of audit evidence : Which of the following is not considered a type of audit evidence? Which of the following is not part of the definition of proportionate liability adopted by the Private Securities Litigation Reform Act?
To ourselves and to our lord and savior jesus christ : The Scripture verse from the Old Testament (Joshua 1:9) says, "Have I not commanded you? Be strong and courageous. Do not be terrified; do not be discouraged, for the LORD your God will be with you wherever you go."
Calculate the effect of waiting on the project risk : Assuming that all cash flows are discounted at 10%, calculate the effect of waiting on the project's risk, using the same data. By how much will delaying reduce the project's coefficient of variation? (Hint: Use the expected NPV.)
Compute the cost per broadcast hour during august : Compute the cost per broadcast hour during August and October for each of these cost items - What will be the total amount incurred for each of these costs during December, when the station's activity will be 480 broadcast hours?
What will be effective rate of interest after the 6 month : You have a $1,100 balance on your 15% credit card. You have lost your job and been unemployed for 6 months. You have been unable to make any payments on your balance. However, you received a tax refund and want to pay off the credit card
Calculate her annual profit and return on investment : Calculate her annual profit and return on investment, assuming that she (A) pays the full $200,000 from her own funds or (B) borrows $150,000 at 5 percent. Then discuss the effect, if any, of leverage on her rate of return.
Write an analysis : Choose a pair of companies from the list below and write an analysis of why you would invest in the common stock of one company over the other.
Prepare the statement of cash flows with a total column : Prepare the statement of cash flows with a total column for the three-year period.- Comment on significant cash flow items in the statement prepared in (a).

Reviews

Write a Review

Managerial Accounting Questions & Answers

  Manage budgets and financial plans

Explain the budgeting process and its importance to a business, identifying the components of different budgets, forecast estimates for inclusion in the budgets.

  Prepare a retained earnings statement

Prepare a retained earnings statement for the year and Prepare a stockholders' equity section of given case.

  Prepare a master budget for the three-month period

Prepare a master budget for the three-month period.

  Construct the companys direct labor budget

Construct the company's direct labor budget for the upcoming fiscal year, assuming that the direct labor workforce is adjusted each quarter to match the number of hours required to produce the forecasted number of units produced.

  Evaluate the predetermined overhead rate

Evaluate the Predetermined Overhead Rate

  Determine the company''s bid

Determine the company's bid if activity-based costing is used and the bid is based upon full manufacturing cost plus 30 percent.

  Compute the pool rates for the different activities

Complete the schedule to compute the pool rates for the different activities.

  Prepare Company financial statements

Prepare Company financial statements

  Prepare an analysis of terracycles

This individual assignment is based on the TerraCycle Inc.

  Discuss the ethical issues

Discuss the ethical issues

  Political resources in emerging markets

Calculate the GDP in Income Approach  and Expenditure Approach

  Management accounting - ehsan electronics company

A new plant accountant suggested that the company may be able to assign support costs to products more accurately by using an activity based costing system that relies on a separate rate for each manufacturing activity that causes support costs.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd