Calculating the cpi, spi and csi

Assignment Help Business Management
Reference no: EM1378043

Question1. A sales project at month five had an actual cost of $34,000, a planned expense of $42,000, and a value completed of $39,000. Determine the cost and schedule variance and CPI and SPI.

Question2. A project to develop a county park has an actual cost in month 17 of $350,000, a planned cost of $475,000, and a value completed of $300,000. Find the cost and schedule variances and the three indexes.

Question3. A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the schedule and cost variances. Re-estimate the variances if the actual cost had been $750,000.

Question4. For the following test marketing project at week 6, calculate the cost, schedule, and time variances. Also, calculate the CPI, SPI, CSI,, and the ETC and EAC.

Activity Predecessors Duration WKs Budget $ Act Cost$ % completed
a -- 2 300 400 100
b -- 3 200 180 100
c a 2 250 300 100
d a 5 600 400 20
e b,c 4 400 200 20

 

Reference no: EM1378043

Questions Cloud

Discuss the effect of any seasonal factors utilizing : discuss the confidence intervals also their usefulness based on the number of data points. Discuss the effect of any seasonal factors utilizing the process performance data collected each week.
Critical safety or security challenges : Assume if there were critical safety or security challenges confronting a zoo environment; what steps would a manager take to overcome them?
Indicates that at least two of the projects must be done : it takes two hours to refill the container also return it to the bathtub. Illustrate what happens to the system over time.
Explore corporate websites that have a recruitment area : Explore 4 to 6 corporate websites that have a recruitment area as well as note their major features and strengths and weaknesses. Create a table that contains
Calculating the cpi, spi and csi : A sales project at month five had an actual cost of $34,000, a planned expense of $42,000, and a value completed of $39,000. Determine the cost and schedule variance and CPI and SPI.
Explain your typical customer''s needs : How has the doubling of your firm's customer base every 6 months affected its ability to maintain this focus on the customer? If this dramatic growth continues, what are some specific actions your firm will take to retain its goal of "focus on the..
Should the organization sell the lease or drill : Four possible outcomes are listed below, together with probabilities also payouts. Should the organization sell the lease or drill. When preparing a claim that is optically scanned, births dates are keyed in with explain how many digits.
Evaluate marginal tax rate : Suppose her marginal tax rate is 40 % this year and next year, and that she can earn an after-tax rate of return of 8% on her investments.
How does victoria''s secret utilize enhancement : How does Victoria's Secret utilize enhancement of the self to attract consumers? Would you imagine males to visit the site as well as females?

Reviews

Write a Review

Business Management Questions & Answers

  Define if you should open the retail shop in this vacant

Define if you should open the retail shop in this vacant space and Include the break-even transactions, CM%, and the break-even dollar amount.

  Discuss impact unionization has on the public sector

Evaluate and discuss the impact unionization has on public sector productivity, both the advantages and disadvantages.

  Strategy-ethics and social responsibility

Assume that you are the sales manager at a European company which makes sleepwear products for children. Company personnel discover that the chemicals employed to flameproof the company's line of children's pajamas might cause cancer if absorbed t..

  Supposing that utilitarian test is ungeneralizable

Supposing that is ungeneralizable and which of these options pass(es) the utilitarian test.

  Would home price data be a discrete or continuous variable

What type of data would you use for the price of homes in a small town and would this data be any different than for the price of homes in a larger area?

  Explain how much will the project''s npv change

Explain how much will the project's NPV change if the number of cars washed is at the expected level

  Cpi and a basket of goods

what is the CPI and a basket of goods - Would you expect the same salary to work in each of these different cities: Denver, San Francisco, New York or Portland?

  Think about a current occasion when you or somebody working

Think about a current occasion when you or somebody working close to you have attempted to introduce as well as manage a change in your part of the organization

  Knowledge management software

Research the Internet for knowledge management software and briefly describe the functions of such software. Find at least two organizations

  Explain and develop a partial risk and mitigation plan

Explain and Develop a partial risk and mitigation plan for three different risks that could be affiliated with a construction project to add a new facility on a college campus

  Explain about economic order quantity technique

Explain what is the Economic Order Quantity technique and what are the basic assumptions the model formula follows?

  Explaining decision-making model

Briefly describe your experience in using the three decision-making models as applied to this scenario.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd