Calculate the expected time and variance for each activity

Assignment Help Operation Management
Reference no: EM131370838

You are responsible for managing an advertising and promotion project with the following activities (times are given in weeks).

Project               Immediate           Optimistic       Most Likely        Pessimistic        Expected        Activity

Activity           Predecessor(s)             Time                  Time                   Time                Time           Variance

A none 2   5 14          B none 8 11 14        C A 5   7   9    

D A 6   9 12          E B, C, D 1   3   5    

a. Using the PERT technique, calculate the Expected Time and Variance for each activity.

b. Using the calculated Expected Times (you may use Most Likely Time if you were unable to complete part a), draw a network diagram labeling each activity with the Letter, Expected Time, ES, EF, LS, and LF. Which activities are on the critical path?

c. What is the probability that the project will be completed within 16 weeks?

Reference no: EM131370838

Was that the ethically correct choice

Years ago in Seattle I worked for an insurance company with just one Jewish employee, who was a good friend of mine. He invented Jewish holidays, taking days off several times

My partner completed the first phase of phone interviews

In applying for a job, my partner completed the first phase of phone interviews, and now the potential employer wants to fly her out for an in-person interview. However, they

Repair shop are battling over who has priority of repayment

Sue got her very first good paying job after college and purchased a very expensive car on credit. A year later, Sue lost her job and was forced to take a lower paying job. Du

What capacity planning issues should the company consider

Budget Travel provides business travel arrangements through 12 metropolitan offices. A key selling point is the firm’s client management database, which includes preferences s

The opportunity to win the bid on large multi-year contract

Your company ACE Construction has been struggling financially but things may be turning around. You have the opportunity to win the bid on a large multi-year contract. One of

Explain the tuckman model of team development

Explain the Tuckman model of team development. Explain the role of conflict in working in teams. Describe one theory of motivation. Describe the elements of planning project c

The furtherance of your career as management professional

Discuss the most important concept, theory, or idea that you have acquired as a result of taking this course. Explain how you plan to use this concept, theory, or ideas in the

Statement would you suggest for three supporting ideas

The vice president of marketing for a major brewing company is aware that college students account for a large proportion of beer sales and that people in this age group form

Reviews

Write a Review

 
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd