Calculate all other variables to three decimal places

Assignment Help Operation Management
Reference no: EM13810917

Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information is presented below indicating the planned schedule and budgeted cost of each activity.

Baseline

Activity Name

% Complete

Duration

(Baseline)

Start

(Baseline)

Finish

(Baseline)

Cost

(Baseline)

Product

0

256 days

6/1/11

5/23/12

 

   Requirements

0

60 days

6/1/11

8/23/11

70,000.00

   Design

0

60 days

8/24/11

11/15/11

   85,000.00

   Build

0

90 days

11/16/11

3/20/12

100,000.00

   Test

0

45 days

3/21/12

5/22/12

60,000.00

   Release

0

0 days

5/23/12

5/23/12

0.00

You have to report project status as of January 31, 2012. The associated schedule and cost information is provided below. Assume a constant resource loading (i.e., planned expenditures are constant over the duration of each activity).

Actual

Activity Name

% Complete

Duration

(Actual)

Start

(Actual)

Finish

(Actual)

Cost

(Actual)

Product

 

215 days

6/1/11

NA

 

   Requirements

100

65 days

6/1/11

8/30/11

68,000.00

   Design

100

70 days

8/31/11

11/20/11

   85,000.00

   Build

80

80 days

11/21/11

NA

90,000.00

   Test

0

0 days

NA

NA

0.00

   Release

0

0 days

NA

NA

0.00

Calculate planned value (PV), earned value (EV), and actual cost (AC) as of January 31, 2012 and answer the questions below. Show all work. Calculate dollar values to two decimal places. Calculate all other variables to three decimal places.

1. What earned value measurement determines whether or not the project is ahead of schedule or behind schedule?What is that value?

2. What earned value measurement determines the project's rate of schedule progress? What is that value?

3. Is the project ahead of schedule, on schedule, or behind schedule? Why?

4. What earned value measurement determines how much the project is under budget or over budget? What is that value?

5. What earned value measurement is used to determine project cost efficiency. What is that value?

6. Is the project over budget, under budget, or on budget? Why?

7. Based on the current project status, what is the estimated total project cost at completion? How much more or less money (other than the current budgeted amount) will you need to finish the project?

Reference no: EM13810917

Questions Cloud

Percentage change in the multifactor productivity : Workers in Center 2 are scheduled to receive a 10% pay raise next month. What will be the change in the multifactor productivity rate? Also, what is the percentage change in the multifactor productivity performance?
What was the concept of amalgamation : What was the concept of amalgamation
What type of powers does the president have that allow : What type of powers does the president have that allow him or her to create and implement various public policies
Create a model to transition an organization through the fol : "Training and Organizational Learning" Give your opinion on the major difference(s) between training and organizational learning. Next, outline a plan to transition an organization with which you are familiar from learning "in" the organization to le..
Calculate all other variables to three decimal places : Calculate planned value (PV), earned value (EV), and actual cost (AC) as of January 31, 2012 and answer the questions below. Show all work. Calculate dollar values to two decimal places. Calculate all other variables to three decimal places.
What was the political importance of this battle for the u.s : What was the political importance of this battle for the United States
Find the distance from the end of the ramp : Find the distance from the end of the ramp to where the jumper lands and her velocity components just before landing - Write down the equation of motion for the skier in the y-direction
Average customer time in the system : What is the average customer time in the system? What would be the effect on customer time in the system of having a second ticket taker doing nothing but validations and card punching, thereby cutting the average service time to 20 seconds?
Explain the difference between roots and routes : The analysis of the psychological process of terrorism is Explain the three phases of terrorism and the significance of understanding terrorism as a psychological process. Explain the difference between "roots" and "routes" regarding individual pat..

Reviews

Write a Review

Operation Management Questions & Answers

  Book review - the goal

Operations Management is about a book review. Title of the book is "Goal". This book has been written by Dr. Eliyahu Goldartt. The book has been appreciated by many as one of those books which offers an insight into the operations and strategic capac..

  Operational plan in hospitality enterprise

Operational plan pertaining to a hospitality enterprise is given in detail in the solution. The operational plan is an important plan or preparation which gives guidelines regarding the role and responsibilities of each and every operation at all lev..

  Managing operations and information

Recognise the importance of a strategic approach to the development and deployment of organisational information systems. Demonstrate an understanding of the importance of databases and their integration to the organisation's overall information mana..

  A make-or-buy analysis

An analysis of the holding costs, including the appropriate annual holding cost rate.

  Evolution and contributor of operations management

Briefly explain Evolution and contributor of Operations management.

  Functions and responsibilities of an operations manager

A number of drivers of change have transformed the roles, functions and responsibilities of an operations manager over recent years. These drivers have not only been based on technological innovations but also on the need for organisations to develop..

  Compute the optimal order quantity

Compute the Optimal Order quantity of DVD players. Determine the appropriate reorder point.

  Relationship to operations practice in the organisation

Evaluate problems in operations and identify approaches to overcoming them. Critically evaluate operating plans and identify areas for improvement. Justify, implement and evaluate changes to operations in line with modern approaches.

  A make or buy analysis

Develop a report for Figi Fabricating that will address the question of whether the company should continue to purchase the part from the supplier or begin to produce the part itself.

  Prepare a staffing plan

Prepare a staffing plan showing the change of your unit from medical/surgical staffing to oncology staffing.

  Leadership styles in different organizations

Ccompare the effectiveness of different leadership styles in different organizations

  Risk management tools and models

Be able to understand the concept of risk, roles and responsibilities for risk management and risk management tools and models.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd