A furnace used in the heat treat operation of cast iron railroad car couplers can hold up to 20 parts. The operation takes an average of 4 hours to process a batch of parts with a standard deviation of 2 hours. The planning department estimates the current demand at 72 parts/day (24-hour day). The parts arrive to the furnace one at a time according to a Poisson stream (i.e., exponential interarrival times).
a) What is the maximum capacity (parts per day) of the heat treat operation?
b) What would be the average cycle time through the operation if we were to use the maximum batch size?
c) What is the minimum batch size that will meet the demand?
d) What would be the average cycle time through the operation if we were to use the minimum feasible batch size?
Analysis of the five economic concepts of Supply and Demand, Strategic Mangement, Organizational Structure, Anti-trust Issues, and Knowledge Economics as they relate to The Success of Google.
Outline a brief memo to defend the value of your department's services to the firm. How could you quantify your claims?
Why is demand forecasting important for effective supply chain management - what are three measures of forecasting accuracy?
When Harley-Davidson implements RFID, it will likely use the technology to help manage its relationships with its main customers, which are the local dealerships that sell motorcycles and use replacement parts in their shops.
dear tutorglobe ltbrgt ltbrgtplease send your quotation and leadtime prior starting the attached assigment as quickly
Assume that a 1.5-day buffer inventory is needed to deal with any production interruptions. Describe the drummer-buffer-rope concept using the Young data to illustrate the process.
Discuss the changes to the ways of working for Phab - i.e. discuss what processes will change, and explore how these might work in practice. You might also consider the changing information needs of the business
Identify logistics management strategies that enable Zara to become so successful - How can Zara maintain its competitive advantage, here the concept of sustainability may be introduced?
Determine the average time a guest spends checking in. How would this change under each of the stated options and which option do you recommend
What are the special issues that complicate the change process within an organization's supply chain performance?
How do you make sense of the teams decline Discuss and Can Wilde turn the team's performance around in two years?
Supply chain strategy
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd