Use the following table to answer the succeeding questions (duration in days):
ACTIVITY
DEPENDENCY
DURATION
A
-
6
B
4
C
B, E
3
D
5
E
A, D
2
F
1
G
7
H
C,E,G
I
J
8
1. Construct the network diagram.
2. State the critical path.
3. What is the duration of the project?
4. State in table format, the ES, LF and slack for activities E, H and I.
5. What would happen to the project if there is a delay of two (2) days in activities B and F?
formal and informal communicationdifferentiate between formal and informal communication and how each affects
Explain the value that each selected project management model offers to a project manager. Explain which project settings are ideal for their use. Use credible sources to support your arguments.
Why is a conductor of an orchestra an appropriate metaphor for being a project manager?
Identify and discuss at four factors that were affecting Tesla's planning and performance.
project management as a careeri need an essay on project management. the only requirements for the essay aremiddotan
capture unidentified riskseeing risks that are not originally identified in a project is essential throughout the life
Project Management Questions
In research, an epistemological stance will influence how you choose a research topic as well as the methodology and methods you use. Review the resources this week to explore the role of epistemology in research.
Develop a risk management plan for school as a school authority - take an example of the recent gun shoot incident in the United States.
Explain what is the relevant cost of the 220 kilograms of the raw material when deciding weather to proceed with the special project.
operating cash flow for a proposed projectestimate the first-year operating cash flow at t1 for a proposed project. the
A company wants to forecast demand using the weighted moving average. If the company uses three prior yearly sales values (i.e., year 2011 = 160, year 2012 = 140 and year 2013 = 170)
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd