What is the critical path for this project

Assignment Help Advanced Statistics
Reference no: EM13321519

1. Allen Machines specializes in developing weed-harvesting equipment that is used to clear small lakes of weeds.  Allen Machines is contemplating the construction of a machine that would harvest weeds on narrow rivers and waterways.  The activities and time in weeks necessary to build one of these experimental machines are shown in the table below.

Activity

Immediate Predecessors

Time in Weeks

A

none

6

B

none

5

C

A

3

D

A

2

E

B

4

F

B

6

G

C,E

10

H

D,F

7

1. What is the minimum possible time required for completing the project?

2. What is the latest possible time that Activity D may be started without delaying the completion of the project?

3. What is the latest finish time for Activity F?

4. What is/are the critical path(s)? 

2. The following is the activity and associated costs for the renovation of the local high school football stadium. The times are in weeks.

Activity

Immediate Predecessor

Time

Cost ($)

A

-

4

25,000

B

-

5

30,000

C

A

3

15,000

D

B

8

50,000

E

B

2

12,000

F

C, D

3

15,000

G

C, D

7

46,000

H

E, F

2

20,000

 1. What is the critical path for this project?

 2. How much of the total budget would be spent in Week 8 (Period 8) with the earliest start budget?

 3. Johnson Construction Company is in the process of installing power lines to a large housing development. The company wants to minimize the total length of wire used, which would minimize the company's cost. The housing development is shown below.  Each house has been numbered, and the distances between houses are given in hundreds of feet.

1022_What is the critical path for project.png

1. What do you recommend to Johnson Construction Company?

7. The storm drains in the Cedar Rapids, Iowa, have been upgraded following the devastating floods of 2008. The network of storm drains and the capacities are shown below. Determine the maximum flow (in hundreds of gallons of water per minute) from node 1 to node 5. Remember that the arc has both capacity and reverse capacity.

From Node

To Node

Fluid Flow

1

2

250

2

1

100

1

3

100

3

1

150

1

4

400

4

1

400

1

5

150

5

1

200

2

4

300

4

2

200

3

4

250

4

3

300

3

5

300

5

3

250

4

5

300

5

4

0

8. From the States Data Setthe following output for the Income in 2000 and for the Income in 2010 was created.

1. Which variable has the greatest relative variation?

9. You are a consultant and the U.S. Department of Laborhas requested assistance in evaluating the impact of economic stimulus on the unemployment rate. From theStates Data Setthe following t test was conducted to answer the question:

"Has there been a significant reduction in the national unemployment rate between January and June?"

1166_What is the critical path for project2.png

1. What is the Null and the Alternative Hypotheses?

2. What is your level of alpha (α)?

3. What is your conclusion?

4. What is your answer to the question?

10. The Governor of a southern state has asked Kaplan Consulting to determine if the state were able to increase the percentage of its population with a Bachelor's Degree to 50%, what might be the expected median household income based on 2010 data? Here is the output from the Regression procedure from Excel.

469_What is the critical path for project1.png

1. What would be the predicted median household income if the percentage of the population in the state were 50% or 50?

199_What is the critical path for project3.png


Attachment:- Unemployment Rates.xlsx

Reference no: EM13321519

Questions Cloud

The necessary components as set forth in the rubric : Complete your Portfolio Project assignment, focusing on making sure that you have all of the necessary components as set forth in the rubric. Spend time making sure that the formatting meets APA standards, and thoroughly proofread and grammar-check y..
Minimum possible time required for completing the project : What is the minimum possible time required for completing the project and what is the latest possible time that Activity D may be started without delaying the completion of the project?
Explain transferred in galvanic cell with platinum bar : Can copper ions be transferred in galvanic cell with platinum bar. why or why not? please provide a detailed explanation
Calculate the change in potential energy of this electron : An electron is released to accelerate from point 1 to point 2 in a potential region. The electric potentials at these points are V1 = -35 V and V2 = +200 V. Calculate the change in potential energy of this electron
What is the critical path for this project : What is the minimum possible time required for completing the project and what is the latest possible time that Activity D may be started without delaying the completion of the project?
The co2 could be produced if the reaction goes to completion : CaO + C --> CaC2 + CO2 [unbalanced] If 244 g of CaO is combined with 318 g C, how many grams of CO2 could be produced if the reaction goes to completion
Calculate rms output voltage of the transformer : A step-down transformer is used for recharging the batteries of portable devices. calculate rms output voltage of the transformer
Is theory z still relevant today : 1) Is Theory Z still relevant today?
What is the water content and liquidity index of the fines : A soil proposed for a compacted fill contains 38% fines and 62% coarse materials by dry weight. when the coars fraction has w=2.0%, its affinity of water is completely satisfied( that is,it is saturated but surface dry).

Reviews

Write a Review

Advanced Statistics Questions & Answers

  Relationship between speed, flow and geometry

Write a project proposal on relationship between speed, flow and geometry on single carriageway roads.

  Logistic regression model

Compute the log-odds ratio for each group in Logistic regression model.

  Logistic regression

Foundations of Logistic Regression

  Probability and statistics

The tubes produced by a machine are defective. If six tubes are inspected at random , determine the probability that.

  Solve the linear model

o This is a linear model. If your model needs a different engine, then you need to rethink your approach to the model. Remember, there are no IF, Max, or MIN statements in linear models.

  Plan the analysis

Plan the analysis

  Quantitative analysis

State the hypotheses that you are going to test.

  Modelise as a markov chain

modelise as a markov chain

  Correlation and regression

What are the degrees of freedom for regression

  Construct a frequency distribution for payment method

Construct a frequency distribution for Payment method

  Perform simple linear regression

Perform simple linear regression

  Quality control analysis

Determining the root causes

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd