What is the critical path for the project

Assignment Help Project Management
Reference no: EM131293131

Microsoft Project Assignment

MS Project 2013 experience required

This assignment consists of two parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the assignment it is written for.

Part A: Project Schedule

(Submit as one Microsoft Project file)

1. Create a multi-level work breakdown structure (WBS) and detailed project schedule, using the information from the "Greendale Stadium Case" located at the end of Chapter 6, and incorporating the following constraints.

Note: When you create your MS Project schedule, you will need to update your project per the following constraints:

o The project must consist of at least twenty (20) tasks.
o Each task must have a start and finish date that matches the duration noted in the assignment.
o Each task must be assigned to a resource (e.g., Demolishing Crew; Construction Crew; Landscaping Crew).
o Assume that the crew works during normal weekdays (no weekend work) under normal conditions (8 hours per day).
o In terms of holidays, you can assume no work will be done the following days: New Year's Day, President's Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year's Eve.

Part B: Written Response

(Submit as a Microsoft Word file)

1. Respond to the following questions in a one to two page paper based on your project schedule.

o When will the project be completed?
o What is the critical path for the project?
o How much slack / float is in your project? What activities have the greatest slack / float?
o Identify the top three activities that you believe could impact the project completion date.
o What additional activities you would add to this project to make it more complete, from a project management viewpoint?

Greendale Stadium Case:

The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the 2014 season. A penalty clause of $100,000 per day of delay beyond May 20, 2014, is written into the contract.

Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said that if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball park with modern lluxury boxes.

Use Table 6.3 to construct a network schedule for the stadium project:

Greendale Stadium Case

ID

Activity

Duration

Predecessor(s)

1

Baseball Stadium

 

 

2

Clear stadium site

70 days

-

3

Demolish building

30 days

2

4

Set up construction site

70 days

3

5

Drive support piling

120 days

2

6

Pour lower concrete bowl

120 days

5

7

Pour main concourse

120 days

3,6

8

Install playing field

90 days

3,6

9

Construct upper steel bowl

120 days

3,6

10

Install seats

140 days

7,9

11

Build luxury boxes

90 days

7,9

12

Install jumbotron

30 days

7,9

13

Stadium infrastructure

120 days

7,9

14

Construct steel canopy

75 days

10

15

Light installation

30 days

14

16

Build roof supports

90 days

6

17

Construct roof

180 days

16

18

Install roof tracks

90 days

16

19

Install roof

90 days

17,18

20

Inspection

20 days

8,11,13,15,19

Reference no: EM131293131

Questions Cloud

What marketing research might have been undertaken : Suggest what marketing research might have been undertaken prior to making the decision to go ahead with such a venture.
Examine the trend over the past few years : What is the current GDP growth rate for the U.S.? Examine the trend over the past few years. What trends interest you? What stage of the Business Cycle would the U.S. economy be in currently given the trends?
Increased your appreciation and understanding of ais : Based upon the material covered from the readings and/or videos from Week 1, highlight the three most important concepts you learned this week and how each of these concepts will help you in appreciating the power of AIS. Be sure to include examples ..
Financial statement information for the beginning of year : Jet Company's summarized financial statement information for the beginning of the year is as follows: Marketable Securities $50,000 All Other Assets $150,000 Total Liabilities $80,000 Total Stockholders' Equity $120,000 During the year, Jet had Reven..
What is the critical path for the project : What is the critical path for the project? How much slack / float is in your project? What activities have the greatest slack / float? Identify the top three activities that you believe could impact the project completion date.
Identify the issues : Identify the rules (Code section, regulations, case authority, administrative rulings (if any)) - analyze the rules in 2 and how they apply to this situation and provide a conclusion as to the likely treatment
Analyze the impacts of these negative shocks : Use the IS-LM-FX diagrams to analyze the impacts of these negative shocks. Indicate the impacts on the following variables: Y, i, E, C, I, TB (int he absence of any government policies).
Dividends revieved by preferred shareholders : Homestead Oil Corp. was incorporated on January 1, 2016, and issued the following stock for cash: Of the total amount of dividends declared during 2017, how much will be received by preferred shareholders? Dividends revieved by Preferred shareholders..
What marketing research might mean to a firm : Laurent-Perrier, number three in terms of worldwide sales of champagne, has been getting its house in order.- Discuss what marketing research might mean to a firm.

Reviews

Write a Review

Project Management Questions & Answers

  Discuss the role of the project manager or team the

research and read an article on recent recipients of the project management institutes project of the year award. write

  How can good packaging help a product

What is it about Monster's logo that makes it effective? - How can good packaging help a product?- Why is labeling an important part of the packaging for energy drinks like Monster?

  What about variability with a percentage

When calculating sample size, how can a researcher decide on the level of accuracy to use? What about level of confidence? What about variability with a percentage?

  Who are the project stakeholders

Defining Project Stateholders - Who are the project stakeholders

  Primary duties of termination manager

Describe the various ways a project may be terminated. Discuss the primary duties of the termination manager?

  Explain the individual and corporate income tax systems

Briefly, explain the individual (personal) and corporate income tax systems.- What is the difference in individual tax treatment between interest and dividend income?

  Toyotas capabilities and core competencies

Toyota: The Once in a Century Challenge and answer three questions: Analyse the case and answer three questions: 1. Analyse the reasons for the problems faced by Toyota in 2009. 2. Identify Toyota's capabilities and core competencies.

  Important information about communication skillsmanagers at

important information about communication skillsmanagers at blue ridge enterprise have been nearly unanimous in

  What strategies would you use as a project manager

What strategies would you use as a project manager to ensure that your team members identify project risks - what motivation strategies would you use and what challenges do you foresee and what strategies would you utilize to overcome these challenge..

  Does the courts opinion give an unlimited right

Does the Court's opinion give an unlimited right to an employee to have a union representative present when the employee is being questioned?

  What would happen to the roic for healthco

What would happen to the ROIC for HealthCo if you included excess cash in its calculation? Why should one exclude excess cash from the calculation?

  What are the criteria for selecting items for analysis

How do you determine if the project is sensitive to the specific items and what are the criteria for selecting items for analysis?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd