Assignment
The following data consists of the actual time used and potential (the best time possible for this review process) to complete each step in the review process. The actual times are based on the review of 30 projects. The potential times are subjective engineering judgment estimates.
Table: Basic Data Review for Construction Project Equipment Arrangement
Cycle Time (hours)
Step
Description
Actual
Potential
Difference
1
Read basic data package
4
-
2
Write, type, proof, sign, copy, and distribute cover letter
21.9
0.5
21.4
3
Queue
40
0
Lead engineer calls key people to schedule meeting
0.25
3.75
5
Write, type, proof, sign, copy, and distribute confirmation letter
25.4
2.1
23.3
6
Hold meeting; develop path forward and concerns
7
Project leader and specialist develop missing information
12
8
Determine plant preferred vendors
9
Review notes from meeting
10
Resolve open issues
106
104
11
Write, type, proof, sign, copy, and distribute basic data acceptance letter
26.5
26.25
Totals
267.8
151.1
116.7
Use the data in the table above and answer the following questions in the space provided below:
1. What are the sources of value-added and non-value-added work in this process?
2. Where are the main opportunities to improve the cycle time of this process, with respect to both actual time used and the potential best times? What strategy would you use?
3. Step 10: Resolve Open Issues required 104 hours (potential) versus 106 hours (actual). Is there an OFI here? Why or why not? If so, how would you attack it?
4. What do you think are the most difficult critical issues to deal with when designing a sound cycle time study such as this one?
What are the cost and schedule variances for the project and What are the SPI and CPI?
How are changes in the company's product mix necessitating changes to the way managers market Kodak's offerings?
Discuss codes of ethics in PR practice using examples to illustrate key points. Explain why there are obvious and clear links to other areas of business.
Give entries to record Operation carryback, assuming a 50% valuation allowance is needed for any deferred tax asset.
You are still in the first 60 days of joining the team. Identify at least one key message to communicate to your team and project stakeholders.
A start - up business that sells coffee. With the information I am sending you I need to do a Cash budget, Pro Forma Income Statement and a Pro Forma Balance sheet .
Reflect upon the project management and teamwork of your group in relation to theory in this area - Would you recommend conducting this differently in the future?
How it is implemented from more of a purist's approach and just touched on the flexibility of the tool - we are going to look at the BSC from more of an adaptive approach. That is to say, how adaptable is this tool given the wide variety of organiz..
Project Planning is one of the most significant aspects in success of a project. As old adage states: "Those who fail to plan, plan to fail."
The CFO has asked you to analyze the projects and recommend which project he should fund and aBC Inc. has a required rate of return of 15% risk adjusted.
Lorraine Banderez, the project manager, has asked you to investigate how other companies have used project management software, particularly Microsoft Project.
What waiting line model would you use to determine the queuing characteristics of buying a ticket for college football game where
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd