One new engineering team is put together for the development of a new product. This new product will be built through an assembly line. The production manager designs the assembly line. He has been advised that the assembly line must be ready in four weeks (20 working days) for a test run. The manager decided to use CPM (critical path method) and has broken down the projects into the following activities, determined their precedence relationships, and estimated normal times:
Activity
|
Immediate Predecessors
|
Normal Time (days)
|
Crash Time (days)
|
Crashing Cost ($/ day)
|
a. organize layout team
|
none
|
5
|
5
|
-
|
b. organize modification team
|
none
|
3
|
3
|
-
|
c. design personnel jobs
|
a, b
|
2
|
1
|
500
|
d. set machinery in place
|
none
|
3
|
1
|
2500
|
e. connect utilities
|
d
|
7
|
4
|
1000
|
f. modify conveyor system
|
c, e
|
4
|
3
|
1200
|
g. train personnel
|
c
|
3
|
3
|
-
|
h. finishing touches
|
f, g
|
5
|
3
|
800
|
i. run test lot
|
h
|
2
|
2
|
-
|
Based on the information provided above, answer the following questions.
1. What is the project earliest completion time in days? Round your answer to the nearest integer.
2. What is the EST of activity g? Round your answer to the nearest integer.
3. What is the LST of activity c? Round your answer to the nearest integer.
4. What is the EFT of activity g? Round your answer to the nearest integer.
5. What is the slack time of activity g? Round your answer to the nearest integer.
6. How many critical tasks are on the critical path (excluding S and T)? Round your answer to the nearest integer.
7. The manager would like to expedite the project by 1 day. According to the crashing data provided in the table, which task should be expedited?
Preparing aggregate production plans
: A local company makes athletic clothing and they are preparing aggregate production plans on a quarterly basis for the coming year for their line of women's wear. They have the following information available to develop a level capacity and a matchin..
|
About the current state of mobile technology
: Imagine that you are the CEO at the firm that you wrote about in Assignment 1 (Mine was 7-11 convenience store). You are preparing for a meeting with the firm's Chief Information Officer (CIO) about the current state of mobile technology as part of ..
|
What is initial interest rate and quantity of loanable funds
: What is initial interest rate and quantity of loanable funds? What is the new interest rate and quantity of loanable funds assuming supply function remains the same? What could cause such a change in the demand for loanable funds?
|
How would you modify the rabin-karp algorithm
: Implement the floor(), ceil(), rank(), and select() (from our standard ordered ST API from CHAPTER 3) for TrieST - Construct a worst-case example for the Boyer-Moore implementation in ALGORITHM 5.7 (which demonstrates that it is not linear-time).
|
Project earliest completion time in days
: 1. What is the project earliest completion time in days? Round your answer to the nearest integer. 2. What is the EST of activity g? Round your answer to the nearest integer. 3. What is the LST of activity c? Round your answer to the nearest integer.
|
Identify the various types of managed care plans
: The paper is due at the end of this learning plan. The paper should be 2 to 3 pages in length. The paper is due by Sunday midnight at the end of the first week. The assignment assesses competency 1. Identify the various types of managed care plans.
|
Global marketplace and market conditions in overseas market
: Chipotle Mexican Grill, the American Mexican food chain restaurant, opened its first restaurant in the United States in 1993. In 2010, Chipotle opened its first restaurant in the United Kingdom in London on Charing Cross. Then, suggest a strategy for..
|
Difference between regular hours and overtime hours
: Which has precedent, a collective bargaining agreement versus Federal, State or local laws/regulations? What is the difference between regular hours and overtime hours as defined by the FLSA?
|
What is the marital communications privilege
: Explain why the psychotherapist-patient privilege is supported by stronger policy justifications than the doctor-patient privilege.
|