Layout of highway curves

Assignment Help Civil Engineering
Reference no: EM13860160

Question 1 Layout of highway curves:

A. is an approximation technique.

B. should be approximated only in areas of dense vegetation.

C. is a precisely calculated method of construction surveying.

D. is similar to construction surveying of a parking lot or access road.

Question 2 The calculation and layout of horizontal and vertical curves:

A. should be done only by experienced surveyors.

B. is a basic fundamental for construction surveyors.

C. should be done only by graduates of this course.

D. is an intermediate level surveying technique.

Question 3 Real time surveying techniques typically are conducted using:

A. a transit and steel tape.

B. a differential level.

C. GPS or a motorized total station.

D. a theodolite.

Question 4 The word grade in construction work means:

A. a proposed elevation.

B. the slope of profile line.

C. cuts and fills.

D. All of the above

Question 5 A route survey is typically prepared for the construction of a:

A. bridge.

B. highway.

C. store.

D. federal post office.

Question 6 The abbreviation BC in terms of a horizontal curve is the:

A. beginning of curve.

B. beginning of construction.

C. curve benchmark.

D. back site of the curve.

Question 7 When staking or laying out a horizontal curve, the total station is typically set up at the:

A. beginning of curve.

B. point of intersection.

C. end of curve.

D. long chord.

Question 8 An uneven or abnormal symmetry observed following the stakeout of a horizontal curve is usually an indication of a:

A. spiral curve.

B. curve embankment.

C. surveying error.

D. high design speed.

Question 9 An offset stake is installed:

A. after the point of intersection.

B. for use as an undisturbed reference to a centerline stake.

C. one station after station 0+00.

D. when the surveyor uses GPS.

Question 10 What is the distance that an offset stake is set from a centerline stake?

A. 2 feet

B. Half the distance from the beginning of curve to the point of intersection

C. 100 feet

D. The distance varies depending on the site

Question 11 Offset stakes are installed to reduce the:

A. amount of construction staking necessary to maintain line and grade for the highway centerline.

B. quantity of vertical curves in a highway survey.

C. size of horizontal curves on a rural highway construction.

D. engineer's design workload.

Question 12 Vertical curves are used in highway construction to provide a:

A. point of intersection between survey stations.

B. method to go over rivers and streams.

C. gradual change between two adjacent grade lines.

D. fun highway to drive on.

Question 13 When staking out a vertical curve, the point of intersection is:

A. the instrument setup point.

B. a point unable to be staked, as it is an extension of the legs of the curve tangents that is in the air or under the ground.

C. where the vertical and horizontal curves come together.

D. equally spaced between the beginning of the curve and the end of the curve.

Question 14 The location of a vertical curve's high and low points are important for:

A. drainage.

B. friction.

C. curve embankment.

D. station intervals.

Question 15 The proposed route of a highway is typically chosen based in part on the:

A. result of the preliminary survey.

B. lengths of horizontal curves along the route.

C. last aerial photograph taken before construction begins.

D. height of the summation of vertical curves along the proposed route.

Question 16 Except for changes in direction, highways are laid out in what station intervals?

A. 25 feet

B. 50 feet

C. 1000 feet

D. 100 feet

Question 17 Clearing and grubbing are done to:

A. ensure the compensator in the automatic level is not stuck.

B. remove trees and vegetation along the proposed route of a highway or linear construction project.

C. clean the total station prior to staking out the highway centerline.

D. maintain a line of site around horizontal curves for faster drivers.

Question 18 A marking on a slope stake of 3:1 indicates:

A. a total of 3 station intervals for every 100 linear feet.

B. three horizontal feet for every one foot of vertical change in grade.

C. an extremely steep class 3 slope embankment.

D. a vertical curve location marker.

Question 19 The indication of a cut on a slope stake means the:

A. grade at the location of the stake needs to be increased in the amount equal to the indicated cut.

B. road must be kept flat in this area.

C. grade at the location of the stake needs to be reduced in the amount equal to the indicated cut.

D. ground is unstable in this area.

Question 20 Layout for line and grade on highway construction projects is usually obtained:

A. one time.

B. two times.

C. when the contractor submits the pay request.

D. as often as necessary, but typically three or more times

Question 21 For a building with a foundation bottom 10 feet deeper than the finished surrounding grade, the original batter boards should be placed at least how many feet from the corners of the building?

A. 10 feet

B. 3 feet

C. 5 feet

D. At the building corners

Question 22 The most important features of a construction project to verify for the final as-built survey prior to completion of the construction project are:

A. roof top pitches.

B. lab cabinetry color.

C. buried pipeline locations.

D. manhole covers.

Question 23 Culvert location offset stakes are typically installed:

A. adjacent to the inlet and outlet of the culvert pipe.

B. adjacent to the culvert center point.

C. within the excavation limits of the culvert.

D. in line with the run of the culvert.

Question 24 Construction surveying layout for culverts is most like:

A. building layout.

B. highway layout.

C. gravity pipe line layout.

D. bridge layout.

Question 25 Bridge construction surveying is usually conducted:

A. using pacing to layout distances.

B. using a high degree of accuracy.

C. in the winter months when the water is frozen.

D. without regard to the connecting highway.

Question 26 Typically, bridge construction layout is initiated with:

A. complex offset distance calculations.

B. offset stakes from bridge centerline.

C. strings or wire from each end of the adjoining highway.

D. coordinate layout of foundation corners or centers.

Question 27 Bridge construction elevation control is first established with level and rod methods:

A. along the bridge span beams.

B. at the foundation of the bridge.

C. along the adjoining highway centerline.

D. at the crown of the pavement over the bridge.

Question 28 How many building corners must be established using coordinate layout prior to setting a transit or total station over one of the corner points?

A. 1

B. 2

C. 3

D. 4

Question 29 Construction surveying for building layout is most crucial for which component of construction?

A. The roof

B. The walls

C. The doors

D. The foundation

Question 30 A batter board is used:

A. to hit trespassers with.

B. to control unruly workers.

C. to install line of site offsets along a building outside wall line.

D. to hold up instrument tripods.

Question 31 For a rectangular building measuring 26 feet long and 16 feet wide, the diagonals from opposite corners should measure:

A. 26 feet and 16 feet respectively.

B. 30 feet, six and 3/8 inches each.

C. 42 feet each.

D. 2 inches different from each other.

Question 32 A rotating laser is used:

A. as an audible site security alarm.

B. to establish a constant elevation or grade plane in its radius of influence.

C. to install building outside wall line offsets.

D. to keep insects away from the construction workers.

Question 33 To maintain vertical control during multistory building construction, measurements are taken using differential leveling or steel taping from:

A. the roof line.

B. the top of the concrete foundation.

C. the batter board.

D. the rotating laser centerline.

Question 34 For vertical alignment of walls, a transit or total station from a wall line offset can be used, as well as:

A. an automatic level and rod.

B. a steel tape.

C. a horizontal curve computation.

D. a plumb bob offset over the top of an outside wall line or corner point.

Question 35 Projects requiring quantity surveying are usually being paid for:

A. by lump sum after project completion.

B. by unit price measured in dollars per unit of measure.

C. with cash.

D. with extremely expensive survey equipment.

Question 36 The final units of measure reported from a quantity survey of an earthwork project would more than likely be:

A. degrees, minutes, and seconds.

B. feet.

C. square feet.

D. cubic feet or cubic yards.

Question 37 Quantity surveying is accomplished by breaking up large complex areas into:

A. squares.

B. circles.

C. simple geometric shapes.

D. triangles.

Question 38 For earthwork volume calculations, the variation in elevation measured in feet is usually accomplished:

A. by numerous differential leveling measurements.

B. using a tape measure.

C. by rounding to the nearest foot.

D. by guessing.

Question 39 A final survey is also known as:

A. a baseline survey.

B. the last hoorah.

C. an as-built survey.

D. a control survey.

Question 40 The final survey must take into account:

A. building corners installed a few feet from original design location.

B. roadway horizontal curves larger than design.

C. constructed variations from the original design.

D. all the above

Reference no: EM13860160

Questions Cloud

All cells contain cytoplasm : Which of these is NOT a true statement? All cells contain cytoplasm. All cells contain DNA. All cells have plasma membranes. All cells contain mitochondria. All cells contain ribosomes. Which of the following is found in eukaryotic cells but not in p..
What is the title if the film adaptation of don quixote : What is the title if the film adaptation of Don Quixote for children?
In chili peppers, a single gene controls the production : In Chili peppers, a single gene controls the production of capsaicin, the "hot" compound. The Aztecs who cultivated peppers recorded 6 different degrees of hotness. If the alleles for this gene show incomplete dominance, how many different alleles ar..
What is the sociological imagination : Why focus on mobile phones in a chapter introducing sociology as a discipline? What is sociology? What do sociologists study? What is the sociological imagination? Durkheim maintains that the sociologist's task is to study social facts. What a..
Layout of highway curves : The calculation and layout of horizontal and vertical curves. Layout of highway curves
Summarizing the conversation in role of big pharma : Write a brief 100-word journal entry summarizing the conversation in "The Role of Big Pharma" discussion forum. Offer and reflect on any conclusions that the class came to regarding the discussion forum topic.
Whats the best way to reach that target market : What's the best way to reach that target market? What product features should you emphasize? How does your product differ from competitors'?
Describe the role of macrophage as antigen : Describe the role of Macrophage as antigen presenting cell in adaptive immune system
Controversy and issue regarding abnormal psychology : Interpret specific symptoms and syndromes from big pharma&rsquos advertising campaigns and critically evaluate and comment upon the necessity of these medications for the indicated psychiatric disorders.

Reviews

Write a Review

Civil Engineering Questions & Answers

  Draw the bending moment diagram and shear force diagram

Use the concept of real work equivalence to compute the vertical deflection at the free end of the cantilever beam shown below. The 12 inch wide beam has a uniform taper and E=3000kips/in^2

  Determine the minimum green time for each approach

A traffic signal control is being designed for a four-leg intersection on a divided highway with the characteristics shown in the table below. Determine an appropriate length of the yellow interval for each approach and how you will provide it.

  What is the minimum settling velocity of a particles

A flow of 125,000 gallons per day enters a sedimentation basin which is 20 feet wide, 60 feet long and 12 feet deep. What is the minimum settling velocity of a particles that will be 100% removed by the basin

  Determine the smooth concrete and the flow gain

Determine the discharge for (a) commercial steel (b) cast iron (c) smooth concrete and the flow gain if the highest capacity pipe material is chosen over the lowest.

  Estimate the total water that will be withdrawn in 2015

Consider a state with a total water withdrawal of 4.5 bgd in 2000. This was distributed as follows: municipal use 1.0 bgd, industrial use 1.5 bgd, and steam electric cooling 2.0 bgd

  Calculate the change in length of a 30m measuring tape made

Calculate the change in length of a 30m measuring tape made of steel when its temperature changes by 84 F. The coefficient of thermal expansion for steel is x = 3.1 x 10^-6 per C

  Determine the location on the wheel at the net acceleration

a wheel rolls to the right with an angular velocity of 2 rad/s while slowing down at a rate of 3 rad/s^2. knowing the wheel rolls without sliding and ignoring the effect of gravity determine the location on the wheel where the net acceleration is ..

  Determine the magnitude and direction of the shear stress

Crude oil, with specific gravity SG=0.85 and viscosityμ = 2.15×10−3 lbf sec/ft2, flows steadily down a surfaceinclined θ = 30 degrees below the horizontal in a film ofthickness h=0.125 in. The velocity profile is given by u =ρg/μ(hy − y2/2)sinθ

  What is the moment in the extension spring when a force

A bar (wih bending rigidity EI) is supported at A and B with length 2a. The bar is fixed at B (length=2a) with a pin support at A (length L=0). Additionally, at A is a torsion spring (spring constant Ca = EI/a) and an extension spring is attached at ..

  How much the person must sell the bond for 6 years

The bond has a maturity date of 10 years from now. How much the person must sell the bond for 6 years from now in order to make a rate of return of 10% per year, compounded semiannually is closest.

  Determine the centroid-moment of inertia and section modulus

THE HOME DEPOT IN RED HOOK ,BROOKLYN IS LOOKING TO RENOVATE THEIR STEEL ROOF TRUSS.YOU HAVE BEEN ASKED TO DETERMINE THE CENTROID,MOMENT OF INERTIA,SECTION MODULUS AND RADIUS OF GYRATION OF THE DOUBLE ANGLE.

  Determine the compression index of the clay

A layer of normally consolidated clay has been filled with 2m of gravel at a unit weight of 17kN/m3 for a long period of time and the settlement of the clay layer monitored giving a total final settlement of 330mm.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd