In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.
Activity
Task
Predecessors
Duration
Activity Cost
A
Sign Contract
None
5 days
$5,000
B
Design Survey
3 days
$1,500
C
Identify Audience
7 days
$1,000
D
Run Survey
B, C
30 days
$6,000
E
Analyze Results
$3,000
F
Create Presentation
G
Present to Client
E, F
2 days
• Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module's lecture.
• What is the duration of the project?
• How much slack is currently available in the non-critical path?
• How long are the project and feeder buffers?
Calculate the present value of a stream of cash flows based on a discount rate of 8%. Annual cash flow is as follows.
How would you characterize the practice in which the movie theater engaged? Does this practice represent fair customer service? How are customers hurt or adversely affected? Should I have followed my manager’s orders and gone along with his request? ..
In a well-written paper, answer the following case study questions, providing an answer of at least 200 words for each question, as well as ample explanation for each subsection
Create a sales forecast for electric fans using selected techniques, Develop Aggregate Production Plan, Master Schedule, and Materials Requirement Plans for electric fans based off the sales forecast. Be sure to include the following
Write a reflection paper (2 - 3 pages, double-spaced) that synthesizes, relative to the theme, concepts from the assignments, readings, outside/additional readings and your own experiences (with citations and reference list in APA format). Topics ..
What are the different types of contracts and how do they impact risk? What contract type puts more risk on the buyer? What contract type puts more risk on the seller?
Examine the influence of web-based information on global citizenship and multicultural understanding. Then, compile a list of three factors you believe should be considered when evaluating Internet sources for use in researching information.
The quality management system that focuses on meeting customers' needs and practices to help build a customer-focused culture along with techniques to enhance design of work processes, process control, and process improvement,
Which of the following statements regarding critical paths is true?
The Canadian Motorcycle Company (CMC) has determined that its customers are very price-sensitive, with the number of motorcycles purchased heavily dependent upon the prices set. The company makes two different styles of bike: the high-end Jet and the..
You have been asked to provide a system for making fresh brownies for a church youth group fund-raiser. Since you are known to be a student at UST, the Youth Council has asked you to plan the brownie project.
the Chair sampled 500 final grades from last yr for each instructor also computed the number of failures per instructor as 13, 11, and 0 also 16 respectively. Compute the upper also lower standard control limits for this chart.
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +1-415-670-9521
Phone: +1-415-670-9521
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd