Reference no: EM13330514

Requirements and Questions

During the lead-time, the vendors advised Shirley that there was a delay in shipments and that the new hardware delivery would be ten weeks from the original receipt of the order.

The data integrity group also found that the process was more time consuming than expected. When the dataintegrity group of four was half way through the previously estimated checking period, they had only completed one quarter of the work.

1. Should Shirley simply proceed with lengthening the time for ensuring data integrity? Explain your answer and discuss any options that she should consider before making her decision.

2. Copy your Part A schedule into a new Part B file and amend the schedule according to the new information given above (i.e. assume that the shipment will be delayed and that ensuring data integrity will take longer). Manually highlight the rows where you have made changes using the "background colour" icon on the task ribbon. This is to allow your marker to locate them easily.

Document any assumptions you make in Part B in the Word document. If the changes create any resource over-allocation issues make sure that you resolve them.

3. What is the new time for the critical path? In your answer include the new date of completion, new duration and compare the new schedule with the original schedule (e.g. how much longer or shorter is the new schedule in comparison with part A).

4. Describe how each of the changes impact upon the project schedule.

5. What effect does each of the changes have on the cost of the project?

 

Reference no: EM13330514

Questions Cloud

Calculate how far does the box go up the hill : A 20kg box is on a level surface pressed against a spring compressed 25cm and with k=1000 k/m. How far does the box go up the hill
How to evaluate the ph at the points in the titration : Calculate the pH at the points in the titration of 40.00 mL of 0.425 M NH3 for the reaction below. NH3(aq) + HNO3 ? NH4+(aq) + NO3?(aq) For NH3, Kb = 1.8x10-5. Enter your answer with 2 decimal places.
What is the mass of the volleyball : When spiking a volleyball, a player changes the velocity of the ball from 4.0m/s to -28m/s along a certain direction. what is the mass of the volleyball
Estimate the magnitude of the force exerted by the club : In a typical golf swing, the club is in contact with the ball for about 0.0010 s. estimate the magnitude of the force exerted by the club on the ball
How each of the changes impact upon the project schedule : What is the new time for the critical path? In your answer include the new date of completion, new duration and compare the new schedule with the original schedule (e.g. how much longer or shorter is the new schedule in comparison with part A).
Evaluate the theoretical yield in grams of the precipitate : Calculate the theoretical yield in grams of the precipitate formed. 3. If the actual yield of the experiment was 90.5 mg, what is the % yield of Ag3PO4
Which system do you recommend they install : Which system do you recommend they install?
Find the magnitude of the net gravitational force : A 100-kg object and a 400-kg object are separated by 4.20 m. Find the magnitude of the net gravitational force exerted by these objects on a 64.0-kg object placed midway between them
What options does shirley have to shorten the project : Shirley is also asked to develop a risk plan for the project. Describe how the risk plan should be used and what information must be included in the risk plan.

Reviews

Write a Review

Project Management Questions & Answers

  Briefly describe the dilemma

Briefly describe the dilemma.

  Designing new it services for business

You have been promoted to manager of a six-member team responsible for designing new IT services for the business.

  Role of project manager in conjunction with project control

What is the importance of project management? Describe the role of the project manager in conjunction with project control.

  Plan for the denver international airport project

Installation of a baggage handling system (BHS) was an important part of the plan for the Denver International Airport (DIA) project.

  Influence of stakeholders in project management plan

Justify the influence of stakeholders in the project management plan and their role in communication planning.

  Net present value of project is positive

Assuming a risk-free interest rate of 5%, which of the following statements about the project is FALSE? The net present value of the project is positive.

  Five reasons productivity hard to improve service sector

What are the five reasons productivity is difficult to improve in the service sector?

  Who should create breakdown

Small project: Who should create breakdown - Who should create the work breakdown structure for the team and describe

  Write a proposal for multicultural management

- Identify the most critical issues faced by managers with regard to the topic and outline solutions to the issues you identify using theories and best practices presented ininternational business subjects.

  Perform a limited scope risk assessment

Perform a limited scope risk assessment of A T & T, the telecommunications giant. Gather relevant intelligence on the company, such as the latest press releases, articles, and SEC 10K filings.

  Deming-s theory on quality embraced by japanese industry

Why was Deming's theory on quality embraced by the Japanese auto industry and rejected by the American auto industry?

  Computing entries to record operation carryback

Give entries to record Operation carryback, assuming a 50% valuation allowance is needed for any deferred tax asset.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd