Find the required diameter of the force main pa

Assignment Help Civil Engineering
Reference no: EM131012172

In the water supply system shown in Fig. Q4, the pumping station (P) delivers the water from the water treatment plant (WTP) to City ABCDE. The water head delivered by the pumps is 28 m. The water level in the pumping station wet well is at 600.00 m. The value of C for all pipes is l00.
The following elevations are known:
A 570.00 m
B 575.00 m
C 573.00 m

1632_pipe.png

(a) Find the required diameter of the force main PA, (dPA), if the pressure at point A is not allowed to drop below 370 kPa.

(b) Determine the required diameter of pipe BC, (dBC), if the maximum allowed head loss in the network ABC is 0.003 m/m.

(c) Calculate the actual residual pressures at points A and C if dPA = 500 mm.

Reference no: EM131012172

Questions Cloud

Something about how money grows over time : Julie needs to pay a $5,000 tuition bill nine months from now. She has some money saved up that she could invest, but she is also considering a trip to Europe. She remembers reading something about how money grows over time, and she wonders if maybe ..
Agreement for sharing profits and losses : Determine how the $ 110,000 net income would be divided under each of the following three independent assumptions as to the agreement for sharing profits and losses. Use schedules of the type illustrated in this chapter to show all steps in the di..
Cash in exchange for common stock : Case Study #1 Succeed Corporation is a business consulting company recently formed by two shareholders. (a) On February 1, 2016, each shareholder contributed $500 cash in exchange for common stock.
List the main denialist claims made by senator inhofe : List the main denialist claims made by Senator Inhofe in GWR text. Compare these two lists and discuss their similarity or difference
Find the required diameter of the force main pa : Find the required diameter of the force main PA, (dPA), if the pressure at point A is not allowed to drop below 370 kPa. Determine the required diameter of pipe BC, (dBC), if the maximum allowed head loss in the network ABC is 0.003 m/m.
Determining the appropriate discount rate for a project : Does the subjective approach to determining the appropriate discount rate for a project always lead the firm to make the right choice when accepting or rejecting a project? Please explain your answer.
Calculate yield to maturity on the bonds : Calculate the yield to maturity on the following bonds. A 8.5 percent coupon (paid semiannually) bond, with a $1,000 face value and 25 years remaining to maturity. The bond is selling at $910. An 5.6 percent coupon (paid quarterly) bond, with a $1,00..
Discuss the tradeoff between dividends and growth : Discuss the tradeoff between dividends and growth; elaborate on the use and limitations of the Dividend-Discount model. What is the efficient markets hypothesis, what are its three forms, and what are its implications?
Implement an activity-based costing system : In conducting interviews and observing factory operations to implement an activity-based costing system, you determine that several activities are unnecessary or redundant. For example, warehouse personnel were inspecting purchased components as t..

Reviews

Write a Review

Civil Engineering Questions & Answers

  Calculate depth h of mud for the concrete retaining wall

calculate the depth h of mud for which the 3m concrete retaining wall is on the verge of tipping about its forward edge A. the density of mud may be taken to be 1760 kg/m3 and that of concrete to be 2400 kg/m3.

  What is the so2 concentration at a sampling point located

If the effective stack height of the plant is 100 m, and the ground reflects the SO2 emission perfectly what is the SO2 concentration at a sampling point located 2 m above the ground in the town.

  Design a drainage and pumping system to deal with mine water

You are required to design a drainage and pumping system to deal with the mine water for the next 10-15 years based on the data in the following sections.

  Determine payback period for an asset that has a first cost

Determine the payback period for an asset that has a first cost of $40,000, a salvage value of $8000 anytime within 10 years of its purchase, and generates income of $6000 per year.

  What is the tce concentration in ppm if the tank is held

What is the TCE concentration in ppm if the tank is held at (a) 4 degrees C and (b) 35 degrees C (c) What is the TCE concentration in ppm if the tank is filled with hexane instead of water

  Determine the head loss for the clean filter bed

The rapid sand filter being designed for Laramie has the characteristics show below. Determine the head loss for the clean filter bed in a stratified condition. Depth = 0.75 m

  Determine the horizontal component of the average impulsive

The last segment of the triple jump tracxk and feild event is the jump, in which the athlete makes a final leap, landing in a sand filled pit. Assuming that the velcity of a 185 lb athlete just before landing is 30 ft/s at an angle of 35 degrees with..

  Which will cause reaction at the bearing to be equal to zero

Determine the magnitude of which will cause the reaction at the bearing to be equal to zero. The bearings are in proper alignment and exert only force reactions on the rod. Set = 600 .

  Compute the crushing strength of concrete estimate the

The concrete cylinder 6 in x 12 in broke incompression at a load of 110000 lbs. Compute the crushing strength of concrete. Estimate the tensile strength and the modulus ofelasticity.

  X y and z coordinates of point b for radial readings taken

Calculate the X, Y and Z coordinates of point B for radial readings taken to B from occupied station A, if the backsight azimuth at A is 25°32'48", the elevation of A = 610.098 m, and hi = 1.45 m

  What is the concentration of the chemical leaving pfr

We have a batch reactor ( r = -k1) with volume of V1. The concentration entering the batch reactor is Co. The batch reactor is operated from t =0 to t = t1. After that the water exits the batch reactor and enters a PFR (r = -k2C) wi..

  Suggest an alternative engineering design solution that

Stormwater controls are typically designed by civil engineers. Stormwater is collected in pipes below the ground and routed to nearby surface water

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd