Describe role manager play in integrating informationsystem

Assignment Help Management Information Sys
Reference no: EM13760982

New Information System Project

Part 1: Initial Plan budget. (Using math for decision-making)

You are a manager with budget authority for a new IT project that is being developed for your department. The project is being developed internally by the company IT staff. You are developing a budget for the project. In this scenario, you will be in integrating information systems and information technology to progress an organization toward their organizational objectives. Consider the information given to determine how much capital you will need to raise to complete this project successfully. Your goal is determine the budget needed to complete the project within the stated timeline and maintain the system through the full five year maintenance contract. Note that the first month of maintenance for the contract starts simultaneously with the start of the project. In this case, you have wisely decided to add a 10% strategic reserve to the development phase of the project.

Part 2: Writing Assignment to explain the tradeoffs during the life of development phase of the project. You will not perform any mathematical calculations for this section of the Assignment. Conduct research to ensure that you understand this concept of the project management triangle. Do not perform any calculations for this portion.

Given:

• IT Project Timeline: 1 January 2016- - 31 March 2017

• 3 weeks of holiday time is planned off during this timeline

• Do not forget the concept of a leap year

• Assume vacation weeks are not paid for the purpose of this problem, as vacation pay is paid and allocated by a separate corporate budget funding source different from the IT Project funding source

• If total weeks are computed as a non-whole number of weeks, round to the nearest week

• Carry out items to the thousands place for fractions (for example 1/3 = 0.333) prior to continuing calculations, then round up or down as needed to whole numbers for final dollar values

• 40 hour work week is the standard contracted work week

• No overtime is allowed to keep costs down

• 10 managers

• 100 union employees

• Manager salary is $100 per hour

• Union salary is $35 per hour

• Systems planning cost is $50K

• System development cost is $1.5M

• System fielding cost is $250K

• System Maintenance (5 year contract, amortized, payments begin at project start) = $5.0M

• Strategic reserve, when (if) applied to the timeline, should also be applied to the maintenance costs during the timeframe of the timeline. However maintenance costs beyond the timeline have been negotiated as a firm fixed priced contract and no longer require the use of strategic reserve in addition to the negotiated price

Answer the following questions: (Show your work):

1 How many work weeks are in the project timeline, where work will actually occur?

2 How much money does the team cost per hour?

3 How much money does the team cost per week?

4 How much money does the team cost for the duration of the IT Project?

5 Remembering that maintenance is amortized, and that payments begin during the first month of the project, and that all other system costs are assigned to the project; what is the total systems cost through the timeline completion on 31 March 2017?

6 What is the total project cost through completion on 31 March 2017?

7 After project completion on 31 March 2017, what will be the remainder cost for maintenance that will still need to be budgeted and managed?

8 Forecasting a budget with no strategic reserve, what should the project cost per month be for the budget during the project timeline?

9 With the addition of a ten % strategic reserve, what should the project cost per month be for the budget during the project timeline?

10 Considering that you decide to budget using the strategic reserve, and you need to budget for the entire maintenance cost, what is the total amount of capital you will need to raise to complete the project successful during the timeline, and then maintain the system through the full five year maintenance contract, noting that the first month of maintenance for the contract starts simultaneously with the start of the project?

Written Portion - Discussion of the project management triangle

An example situation:

The project manager has come to you with the following:

1 Some of your employees who will be using the system have suggested changes, which will end up improving the system but will take longer to develop and implement. She feels that they would be beneficial changes.

2 Two of her developers and one of her managers have left to work for another company. The company has a hiring freeze so she is unable to replace them. This will most likely add time to the project but it will also result in small savings in terms of labor cost.

You are also the aware of the following information:

1 When the budget was approved there was a strategic reserve to allow for contingencies.

2 You have some additional discretionary funds which you were hoping to be able to use them for bonuses for you employees at the end of the year.

3 You have a lot of faith in the project and believe that it will eventually improve the productivity of your employees. He also realize that it will take time after the project is fully implemented for this productivity to be realized and that there is a likelihood that it will actually decrease for a couple of months while people are learning the new system.

4 You know that you have a number of people in your department that are nearing retirement and are not in favor of having to learn a new system.

To meet the requirements of this Assignment, write an APA style paper in which you take the role of manager to discuss the pros and cons of making any changes to the plan regarding the initial goals of performance, cost, and schedule. For the paper do not do any calculations. The facts presented are examples of the types of situations that you might encounter. You do not have to address these situations.

Limit your discussion to the tradeoffs among these three areas. How do performance, cost, and schedule interact? Discuss the concept of the project triangle, also called the triple constraint, or iron triangle.

Ensure you turn in your unit Project as a single Microsoft Word document, in APA format, with a cover page and reference page citing at least two online references on the unit concept topics and the eBook as a reference. Your work should compose 2-3 pages of content (double spaced, 12 point Times New Roman font).

This Assignment addresses the following outcomes:

- Describe the role manager's play in integrating information systems and information technology (IS/IT) within an organization.

- Solve business problems using information systems.

- Solve real-world problems using mathematical skills.

Reference no: EM13760982

Questions Cloud

Summary of best technology timeline : Summary of Best technology timeline and example on the given technology
Global health : The intevention mapping models.imagine that you are a health educator or other health profeeionals that is planning a prevention programs that relates to the Healthy People assigned focus area.
What is the optimal level of output for a monopolist : Question #2A monopolist faces a demand given by p = 30 - 3y. Its cost function is c (y) = 3y 2 + 6 y a) What is the optimal level of output for a monopolist? b) What is a monopolist price?
Critical components of a marketing plan : Strengths, weaknesses, opportunities, and threats (SWOT) are critical components of a marketing plan. For this assignment, you will build a marketing plan for an organization, product, or service of your choice.
Describe role manager play in integrating informationsystem : Describe the role manager's play in integrating information systems and information technology (IS/IT) within an organization. - Solve business problems using information systems. - Solve real-world problems using mathematical skills
Research erp to determine what its purpose is : Research ERP to determine what its purpose is. Also, determine what problems have been encountered when different companies in different industries have implemented this kind of system.
Firms that make game systems like playstation : Firms that make game systems like Playstation and Nintendo typically charge a price close to average cost on the game system itself, and do not change that price even when the systems are scarce or demand increases. Why might this be a profit-maximiz..
Research budget planning and control : Use the Internet to research budget planning and control. Imagine that the company that you currently work for, have previously worked for, or would like to work for in the future has tasked you with preparing a budget plan.
Potential and kinetic energy : Find the potential energy (PE) for each ball on each ramp.  In this lab mass is given in pounds and height is in feet, so use 32.2 ft/sec2 as the gravitational constant.

Reviews

Write a Review

Management Information Sys Questions & Answers

  Service operations queues compared to buffering

service operations queues compared to buffering inventorieshow are people waiting in queues in service operations

  Analyze case study - the cliptomania web store

Show the strategic issues faced by the company in launching and developing their e-business venture. Provide your recommendations and analysis.

  How would this affect training of is personnel

Consider this statement: "IS personnel need a combination of skills - one-third technical skills, one-third business skills, and one third communications skills." Do you think this is true? How would this affect training of IS personnel

  Important resource in the health care facility

Justify the function of a master patient index. Discuss how the master patient index is an important resource in the health care facility

  What are some strengths of computer systems

Strengths of computer systems and What are some strengths of computer systems and technology use, including hardware and software?

  Prepare a variance analysis report

Prepare a variance analysis report based on the information

  Explain why openid offers users greater convenience

Explain why OpenID offers users greater convenience and security than the current system. Would you consider using an identity provider to access content on the Web? Why or why not

  Online professors response to marketing managementdiscuss

online professors response to marketing managementdiscuss the strengths and weaknesses of personal selling and describe

  Technology impactsvocal artists these days ofrten rely on

technology impactsvocal artists these days ofrten rely on technology to get them that platinum record. these days you

  How has the ehr changed the way healthcare functions today

You have learned a great deal about the roles and functions of the electronic health record (EHR) in healthcare. How has the EHR changed the way healthcare functions today

  How technology support functions of management

What are some examples of how technology has supported each of the functions of management

  Dominos sizzles with pizza tracker case study1 what is

dominos sizzles with pizza tracker case study1. what is dominos business model? how successful has it been?2. what

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd